020What does a blue Texas mean for the data center boom?
Democrats won Texas’s races for governor and US Senate on Tuesday: the AP called both for Gina Hinojosa and James Talarico, and Gov. Greg Abbott conceded. The freeze came first: since August, Abbott’s audit has held every large data center (75 MW or more) waiting to switch on in ERCOT, and since September his order to the state’s environmental agency has been read to cover the permits for the gas plants that let campuses skip the queue. In our base case Hinojosa leaves Texas with about 2.2 GW less new data center load switched on at the end of 2027 than Abbott’s path would have, and 2.9 GW less at the end of 2028 (2.0–5.9 GW, depending on the races still being counted and how long a moratorium lasts). That is on top of the roughly 2.2 GW Abbott’s freeze already costs at each date. About half the gap is grid load in ERCOT’s Batch Zero arriving later; per GW, the hardest hit are self-powered campuses for Microsoft, Anthropic and OpenAI whose air permits are pending or still to come.
The results so far
As reported late on Nov 3. Calls are the AP’s unless noted; shares are from the time shown in each row and will move as counting finishes.
Texas froze its own boom
Hinojosa inherits a pipeline her Republican predecessor had already stopped. On August 3, Gov. Greg Abbott told the Public Utility Commission and ERCOT to audit every data center seeking a grid connection and to deny any that failed. ERCOT stopped approving data centers of 75 MW or more to switch on. Seventeen loads, about 6.6 GW, had cleared every step but that one; none has been approved since. ERCOT slates a cohort of 17 loads, which we take to be the same ones, for the second quarter of 2027. ERCOT also halted Batch Zero, the first round of its new process for large loads, which holds 194 GW in its base and studied groups.
On September 21 the freeze reached the workaround. Abbott told the Texas Commission on Environmental Quality to stop issuing permits for data centers until the audits finish, and law firms read that to include the on-site gas plants that let a campus skip ERCOT’s queue, but not permits already issued. Enforcement has been leaky: watchdogs counted air notices and stormwater approvals after the order; TCEQ later said the permits issued since then had been suspended, and shut its automatic e-filing system. Abbott kept the pause after President Trump called it a mistake. ERCOT files its audit on December 10, and the commission takes it up on December 17, five weeks before Hinojosa is sworn in.
The freeze came first
Official actions and campaign plans on data centers in 2026, and the dates that decide what replaces the freeze.
- Patrick’s interim chargesSenate committees told to study data centers’ water and power demands and the cost of their sales tax exemption
- Abbott’s data center packageAsks the 2027 Legislature to repeal the sales tax exemption and make data centers add generating capacity, pay for their own interconnection, use water-efficient cooling such as closed loops and report power and water use
- Talarico’s planRepeal the sales tax exemption, make large users pay for their own grid costs, closed-loop cooling, local approval or rejection, federal minimum standards
- Hinojosa calls for a moratoriumAsks Abbott to halt new data centers by executive order until the Legislature passes protections
- Senate Finance hearingSenators from both parties question the sales tax exemption; whether existing certifications would be honored is left open
- ERCOT audit and pauseAbbott directs the PUCT and ERCOT to audit every data center in the queue before approving more; ERCOT postpones its Batch Zero study
- Trump calls the pause a mistakeIn an interview reported Aug 9–10; Abbott keeps it
- Water reporting enforcedAbbott directs the Texas Water Development Board to enforce its water-use survey and refer data centers that skip it to prosecutors
- PUCT large-load ruleLoads of 75 MW or more post $50,000 per MW of security and pay a $100,000 initial fee plus study charges
- TCEQ permits haltedAbbott tells TCEQ to stop issuing permits for data centers until the ERCOT and water audits finish; law firms read the halt to reach on-site gas plants
- Attorney general opens an inquiryInto developers in 18 counties that skipped the state’s water survey
- Paxton’s plan reportedBacks Abbott’s state-level proposals and repealing the exemption; own power, closed-loop cooling, a China ban
- Election dayThe AP calls the governor’s and Senate races for Hinojosa and Talarico; Abbott concedes
- ERCOT audit reportsEligibility and community-impact reports filed with the PUCT
- PUCT open meetingThe commission takes up the audit; Abbott still governor
- Transmission-cost rule dueSB 6 deadline; the proposal bills large loads on 12 monthly peaks instead of 4, with a 20-year minimum
- New US Senate sworn in
- 90th Legislature convenes
- Governor inaugurated
- Session endsDay 140
- Veto deadline20 days after the session ends
- Most new laws take effectUnless passed with two-thirds for immediate effect; two utility commission terms end
Most of the rulebook is already agreed
Abbott’s June package, Paxton’s Senate plan and the Democrats’ plans overlap more than the campaigns suggest. Abbott, Paxton, Talarico and Hinojosa would all repeal the data center sales tax exemption, which state projections put at $1.3 billion or more in 2026 (the comptroller counts 121 data centers using it). Abbott, Paxton and Talarico would also make data centers pay for their own power and grid connections, and Hinojosa would protect households from rate increases driven by data centers. Senators of both parties questioned the exemption at a July hearing; whether existing certifications would be honored was left open. Both sides’ plans put those rules before the 2027 session.
What Democrats add is narrower: a moratorium until laws pass (Hinojosa by executive order, Goodwin through a special session), a local veto over projects (Talarico, Hinojosa; Goodwin wants residents consulted), union labor on construction (Hinojosa) and, from the Senate seat, federal minimum standards (Talarico).
Both parties want most of the same rules
What each statewide candidate proposed for data centers, or did in office, as reported through October. proposed or did it · partly, or a narrower version.
| AbbottR · Governor | HinojosaD · Governor | PaxtonR · US Senate | TalaricoD · US Senate | PatrickR · Lt. governor | GoodwinD · Lt. governor | |
|---|---|---|---|---|---|---|
| Repeal the data center sales tax exemptionPatrick ordered a Senate study of its cost; Goodwin attacks the incentives and wants a special session on costs. Neither has said “repeal” in coverage we found | ||||||
| Data centers pay for their own power and grid connectionHinojosa would protect households from rate increases driven by data centers; Goodwin opposes households paying for grid buildout | ||||||
| Closed-loop cooling or water priority for residentsHinojosa’s plan targets nondisclosure of water use rather than cooling design; Patrick ordered a study of data centers’ water demands | ||||||
| Disclose power and water useAs attorney general, Paxton opened an inquiry into developers that skipped the state’s water survey. Talarico would publish records of data centers’ tax breaks and include transparency in federal minimum standards; his plan as reported has no power or water reporting | ||||||
| Pause new approvalsAbbott’s pause runs until the audits finish; Hinojosa’s and Goodwin’s until the Legislature passes protections. Paxton backs Abbott’s state-level proposals but hasn’t addressed the pause in coverage we found | ||||||
| Local power to approve or reject projectsAbbott requires setbacks; Paxton backs limits near rural homes and rules on noise and lighting; Goodwin wants nearby residents consulted. None of the three proposes a local veto | ||||||
| Licensed, union labor on construction | ||||||
| Federal minimum standards for data centers | ||||||
| Ban Chinese technology in data centers |
What Hinojosa can actually do
Less than the campaign suggests in 2027, and more by 2028. A governor can’t write statute: the session that opens January 12 needs the Legislature, and the Texas House went into the election 88–62 Republican. Her levers are directives and appointments. Abbott’s freeze is a set of letters, which a successor can keep, rewrite or rescind, but the agencies’ commissioners decide how to act on them, and she can’t remove the ones Abbott appointed: only the governor who made an appointment can, with two-thirds of the state Senate.
The utility commission turns over faster than that suggests. A new governor can name its chair as soon as she takes office. Two of its five commissioners appear to be Abbott recess appointees who need two-thirds of the Senate by May 31 or lose their seats, a third appears to be serving past an expired term, and two terms end on September 1, 2027. Recess appointments after the session could give Hinojosa a majority of the commission by late 2027 without a Senate vote, on one reading of the constitution that hasn’t been tested. That matters less for the 2027 freeze than for the rules that follow it: Batch Zero’s allocations, the next batch and who pays for transmission. At TCEQ, one of three seats turns over in August 2027.
How far a letter goes is already in question. ERCOT and the commission complied with Abbott’s, yet a former ERCOT market monitor doubts its requirements can be enforced without new laws, and both agencies asked lawmakers for more authority. A successor’s order would meet the same doubt, from agencies she didn’t appoint, and probably a lawsuit. That is why our paths assume only part of a Democratic moratorium holds, and more of it the more offices Democrats win.
Most of the queue was never coming
ERCOT’s large-load pipeline by stage, from its September Batch Zero classification and monthly reports, with the named self-powered campuses whose permits are pending. ERCOT’s stages are separate counts on different dates, so they don’t add up to a total.
Data
| Stage | GW | Projects | What it means |
|---|---|---|---|
| Switched on since 2022 | 9.5 | — | Large loads of all kinds (data centers, crypto, industrial and others) ERCOT has approved to energize since 2022; 4.4 GW drawn at July’s peak. Unchanged through September. |
| Cleared, waiting to switch on | 6.6 | 17 | Finished every ERCOT step except approval to energize (Aug 20). ERCOT’s Nov 1 cohort, also 17 loads (about 6.9 GW), is slated for Q2 2027; we assume they are the same loads. None approved since Aug 3. |
| Batch Zero base load | 66.4 | 204 | All required ERCOT studies approved; modeled as given. Conditional on the audit. |
| Batch Zero, to be studied | 127.9 | 158 | A qualifying study submitted; each gets a 2028–32 allocation, possibly zero. ERCOT’s slides give 125.4–127.9 GW. |
| Excluded, to Batch One | 302.2 | 373 | No qualifying study or dynamic model by Jul 10; deferred to Batch One, which ERCOT targets to launch in June 2027. Preliminary until the audit. |
| Own gas, permit pending | 6.7 | — | Named self-powered campuses whose air permits were pending on Sep 21 (Nexus for Anthropic, Frontier for OpenAI and Oracle, Microsoft’s Abilene expansion by our attribution) or that will need them (Microsoft’s Pecos campus, Fluidstack’s Cameron County site). Mixes plant and IT capacity as each project reports it. |
The 474 GW is a list of requests, not a pipeline: more than five times ERCOT’s record peak of about 91 GW. ERCOT’s 2025 forecasting method counted new data center requests at 49.8%, and only about 46% of the large load it has approved since 2022 showed up at July’s peak. So the freeze matters less for the headline number than for the few dozen GW with studies, tenants and money behind them. We model those: the cleared loads, Batch Zero’s base load at ERCOT’s 49.8% realization, and the named self-powered and out-of-ERCOT campuses. That puts about 17.2 GW of new data center load on before the end of 2028 had nothing been frozen, and 14.9 GW on Abbott’s path.
What Hinojosa adds to the delay
New data center load switched on in Texas after September 2026, GW, before the freeze, on the path Abbott had set and under Hinojosa. Pick which other races Democrats win and when a moratorium ends; the base case is Hinojosa alone, with a Republican lieutenant governor and House, and a moratorium that ends in September 2027.
About 2.2 GW less switched on by the end of 2027 than on Abbott’s path and 2.9 GW less by the end of 2028; about 1.0 GW never built by 2030. Grid approvals wait about 3 months longer, own-gas permits about 4 months.
Data
| Quarter end | Before the freeze | Abbott’s path | Hinojosa | + Goodwin | + Texas House |
|---|---|---|---|---|---|
| Sep 30, 2026 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
| Dec 31, 2026 | 0.4 | 0.2 | 0.2 | 0.1 | 0.1 |
| Mar 31, 2027 | 1.4 | 1.0 | 0.7 | 0.6 | 0.5 |
| Jun 30, 2027 | 3.2 | 2.3 | 1.8 | 1.6 | 1.5 |
| Sep 30, 2027 | 5.5 | 3.3 | 2.7 | 2.6 | 2.5 |
| Dec 31, 2027 | 8.0 | 5.8 | 3.7 | 3.5 | 3.3 |
| Mar 31, 2028 | 10.3 | 8.0 | 5.9 | 5.1 | 4.7 |
| Jun 30, 2028 | 13.0 | 10.3 | 8.0 | 7.2 | 6.7 |
| Sep 30, 2028 | 15.1 | 12.6 | 10.0 | 9.2 | 8.7 |
| Dec 31, 2028 | 17.2 | 14.9 | 12.1 | 11.1 | 10.5 |
| Mar 31, 2029 | 19.1 | 17.0 | 14.5 | 13.4 | 12.6 |
| Jun 30, 2029 | 21.0 | 18.9 | 16.4 | 15.5 | 14.7 |
| Sep 30, 2029 | 22.9 | 20.8 | 18.4 | 17.4 | 16.6 |
| Dec 31, 2029 | 24.8 | 22.8 | 20.2 | 19.2 | 18.4 |
| Mar 31, 2030 | 26.5 | 24.6 | 22.0 | 21.0 | 20.1 |
| Jun 30, 2030 | 28.1 | 26.3 | 23.7 | 22.7 | 21.7 |
| Sep 30, 2030 | 29.8 | 27.9 | 25.4 | 24.3 | 23.4 |
| Dec 31, 2030 | 31.4 | 29.6 | 27.1 | 26.0 | 25.0 |
Democratic columns use a moratorium that ends in September 2027.
On Abbott’s path the commission acts on the audit in December, switch-ons and permits resume early in 2027, and the 2027 session writes his package into law. Texas adds about 5.8 GW of new data center load by the end of 2027 and 14.9 GW by the end of 2028. With Hinojosa sworn in on January 19, a moratorium on new data centers runs until the Legislature passes protections she signs. In the base case approvals wait about 3 months longer and own-gas permits about 4, which leaves Texas 2.2 GW short at the end of 2027 and 2.9 GW short at the end of 2028, with about 1.0 GW never built by 2030. If Goodwin’s lead for lieutenant governor holds, the gap at the end of 2028 is about 3.8 GW.
The range runs from 2.0 GW at the end of 2028, if the moratorium ends when the session does, to 5.9 GW if Democrats also win the lieutenant governor’s office and the Texas House and the moratorium lasts to the end of 2027. Most of the gap is time, not cancellations: the GW come later. The hardest hit are self-powered campuses, where the governor’s environmental agency is the gate: on Abbott’s path about 2.8 GW of them is running by the end of 2028; in the base case, 1.6 GW.
Whose campuses carry the risk
Texas capacity by company, split by what it is waiting on; Batch Zero base load, whose required studies are approved, counts as approved. GW are near-term phases as each project reports them (IT, facility or on-site generation), so the bars compare exposure, not exact load. Hover or tap a bar for the projects.
Self-powered campuses are the most exposed
The irony of the freeze is that the campuses built to avoid the grid are the ones a governor reaches most directly. ERCOT’s pause runs through a utility commission whose members a new governor can replace only as their seats come open; TCEQ’s permits are where a governor’s letter has already worked. Five campuses were waiting on air permits, or will need them:
- Anthropic’s Hill County campus (Nexus): a 1.6 GW gas plant, with about $15 billion of senior debt that Google agreed to guarantee, per Bloomberg; its major-source permit drew a hearing request in October.
- Microsoft’s 900 MW Abilene expansion with Crusoe, first building due mid-2027, where a pending permit for added generation appears to cover its plant (our reading of a TCEQ notice that names Crusoe), and its Pecos campus with Chevron, about 2 GW from 2028, where a minor-source authorization is in review and we found no filing yet for the main air permit.
- OpenAI and Oracle’s Frontier in Shackelford County, where VoltaGrid’s major-source air permit for the site is pending; its first engines were approved in 2025.
- Fluidstack’s Cameron County site, up to 1.5 GW with on-site generation that will need permits, in the county with the most Batch Zero base and studied load; its tenant isn’t named.
Grid-tied campuses carry timing risk, not existential risk. Some hold ERCOT approvals or base-load status: Galaxy’s Helios for CoreWeave, IREN’s Sweetwater, Cipher’s Colchis and Crusoe’s Childress site for Meta. Others’ ERCOT status isn’t public: Cipher’s Barber Lake, Google’s Armstrong and Wilbarger campuses and Amazon’s Comanche Peak site, which Vistra says the pause doesn’t affect. Most of their dates hinge on December 17. Amazon’s GW Ranch already holds its 7.65 GW air permit, which makes it one of the least exposed large projects in the state. Fermi’s risk is its own: its only announced lease isn’t in force.
A longer freeze also has winners. Every megawatt already energized in Texas becomes scarcer: IREN’s Childress site, Cipher’s Black Pearl for AWS and Core Scientific’s Denton campus could command better terms on new or renewed contracts as new supply slips, and capacity outside Texas gets a political-risk premium it didn’t have a year ago.
The projects
Named Texas campuses of about 200 MW or more, what each is waiting on and our read of its exposure to Hinojosa relative to the path Abbott had set. Capacity is as each project reports it.
| Project | Who | Capacity | Power | Waiting on | Exposure |
|---|---|---|---|---|---|
| Nexus HubbardHill County | Nexus; Anthropic tenant; Google agreed to guarantee about $15B of senior debt (Bloomberg)GOOGL | 1.6 GW gas plant (build-out 6–8 GW) | ERCOT area, own gas plant | Major-source air permit: comments closed Oct 23, hearing requested; paused | High |
| Frontier (Stargate)Shackelford County | Vantage, VoltaGrid; Oracle for OpenAIORCL | 1.4 GW IT | Off-grid gas | VoltaGrid major-source air permit (notice Sep 22) paused; first engines approved in 2025 | High |
| Abilene expansion (Microsoft)Taylor County | Crusoe; MicrosoftMSFT | 0.9 GW (672 MW IT) | Own 900 MW plant | PSD air permit for added generation under review, paused (our attribution) | High |
| Pecos campus and Project KilbyReeves County | Chevron, Engine No. 1; Microsoft 20-year PPAMSFT, CVX | ~2 GW DC (2.67 GW gas) | Islanded gas | Final investment decision by end-2026; a minor-source authorization in review, no main air permit filing found | High |
| Cameron County campusCameron County | Fluidstack; tenant not named | Up to 1.5 GW | ERCOT plus own generation | ERCOT switch-on and permits for on-site generation; no permit filing found | Medium |
| Milam County (Stargate)Milam County | SB Energy (SoftBank); OpenAI 1.2 GW lease9984.T | 1.2 GW | ERCOT plus new generation | ERCOT switch-on (inferred); building 1 was due Oct 2026 | Medium |
| Childress “Project Hyper”Childress County | Crusoe, Lancium; Meta (reported)META | 1.0 GW | ERCOT | 1 GW interconnection approved; switch-ons after the audit | Medium |
| Armstrong County (Goodnight)Armstrong County | Crusoe; GoogleGOOGL | ~1.07 GW (secondary) | ERCOT plus co-located wind and on-site gas | Switch-ons for buildings due 2027–28; a 525 MW curtailment obligation behind one wind farm; 933 MW of on-site gas turbines reported under construction (secondary) | Medium |
| Wilbarger County “Project Rise”Wilbarger County | GoogleGOOGL | ~0.85 GW (secondary) | ERCOT plus AES generation | Switch-on (likely in the paused group) | Medium |
| Comanche Peak campusSomervell County | Amazon; Vistra 20-year PPAAMZN, VST | 1.2 GW PPA | ERCOT, nuclear PPA | Energize 2027; Vistra says the pause doesn’t affect it | Medium |
| HeliosDickens County | Galaxy; CoreWeave leases Phases I–IIIGLXY, CRWV | 1.6 GW approved; 2.6 GW more in study | ERCOT | Phase II (260 MW IT) from Q2 2027 and Helios II (830 MW, no tenant) need switch-ons; 2.6 GW in study | Medium |
| Barber LakeMitchell County | Cipher; Fluidstack with a Google backstop, then an AI labCIFR, GOOGL | 0.3 GW (207 MW IT) | ERCOT | Halls due Q4 2026–Q1 2027 need switch-ons | Medium |
| Colchis and Cipher’s other sitesWest Texas | Cipher; no tenant namedCIFR | 1 GW base + 1.6 GW in study | ERCOT (AEP) | Batch Zero base load (Colchis, 2028) and studied load; plans for up to 2.5 GW of on-site gas would need TCEQ | Medium |
| SweetwaterNolan County | IREN; no tenant namedIREN | 2 GW (1.4 GW substation energized) | ERCOT | Batch Zero base load awaiting verification; first 300 MW due Q4 2027 | Medium |
| Beacon PointNueces County | Hut 8; investment-grade tenant not named (704 MW IT leased)HUT | 1 GW campus | ERCOT | Batch Zero base load (secondary source); phase 1 timing undisclosed, phase 2’s first hall Q2 2028 | Medium |
| El Paso campusEl Paso County | Meta; El Paso Electric’s 366 MW McCloud plantMETA | ~1 GW | WECC (El Paso Electric) | PUCT vote on McCloud; judges back it only if Meta bears the cost | Medium |
| San Antonio off-grid pairBexar County | Vantage, VoltaGrid; tenant not named | 0.42 GW gas | Off-grid gas | Minor-source permits issued; notice of intent to sue over source splitting | Medium |
| CloudBurst San MarcosGuadalupe County | CloudBurst; tenant not namedET | 1.2 GW | ERCOT area, Energy Transfer gas | Grid or own-gas approvals, mix not disclosed | Medium |
| Caldwell ValleyCaldwell County | Tract; tenant not named | Up to 4 GW; 360 MW first | ERCOT | Later ERCOT batches; a gas plant would need TCEQ | Medium |
| Stargate AbileneTaylor County | Crusoe, Lancium; Oracle for OpenAIORCL | 1.2 GW | ERCOT | Last buildings due by end-2026; a turbine amendment is paused | Low |
| GW RanchPecos County | Amazon; Pacifico EnergyAMZN | 1 GW phase 1 (7.65 GW gas permitted) | Off-grid gas, grid later | Air permit issued Jan 2026; a later grid tie would be exposed | Low |
| Childress (Horizon)Childress County | IREN; Microsoft $9.7B contract, Nvidia $3.4BIREN, MSFT | 0.75 GW grid connection | ERCOT | Energized site; AI halls through 2027 | Low |
| Black Pearl and StingrayWinkler and Andrews counties | Cipher; AWS leasesCIFR, AMZN | 0.3 GW + 0.1 GW | ERCOT | Black Pearl energized and ramping; Stingray’s shell due in Q4 (Cipher) | Low |
| RockdaleMilam County | Riot; Anthropic (per Bloomberg) 20-year leaseRIOT | 191 MW IT | ERCOT | Built on an energized mining site; 96 MW Dec 2027, 95 MW Jun 2028 (secondary) | Low |
| DentonDenton County | Core Scientific; CoreWeaveCORZ, CRWV | ~0.36 GW | ERCOT | Operating | Low |
| MeitnerGray and Roberts counties | Google, IntersectGOOGL | ~0.84 GW (secondary) | Panhandle, own gas firming | Gas permit appears issued in May | Low |
| Project MatadorCarson County | Fermi; TensorWave lease not yet effectiveFRMI, AMD | 2 GW target by end-2027 (11 GW plan) | SPP plus own gas | Lease financing; a further 5 GW air permit was filed in March, status not found | Company risk |
| Project HorizonPecos County | Poolside; CoreWeave exitedCRWV | 2 GW | Own gas (planned) | No anchor tenant since April | Stalled |
| Comanche CircleHood County | Sailfish; no tenant | Up to 5 GW | ERCOT plus planned gas | County rejected its settlement Oct 13; NRG withdrew the gas plant | Stalled |
The Senate seat matters less, for now
Democrats needed a net gain of four seats for a Senate majority, and NBC and CBS project they got it, with Talarico’s seat among the gains; NBC also projects a Democratic House. Even with both chambers, bills face a Republican president’s veto until 2029, so Talarico’s federal minimum standards for data centers are a long shot. What changes sooner is confirmations, including FERC and NRC commissioners, and the ability to block a federal bill preempting state AI or data center rules.
ERCOT sits largely outside FERC’s wholesale jurisdiction, so Washington’s reach into the Texas buildout runs mainly through much of the Panhandle and El Paso, which belong to the SPP and WECC grids. For the campuses in this pack the governor matters far more than the senator.
Democratic governors have gone both ways
Facing the same backlash, two Democratic governors made opposite calls this year. In July, New York’s Kathy Hochul ordered a pause on new permits for data centers of 50 MW or more, for about a year while the state writes an environmental review process. In April, Maine’s Janet Mills vetoed a moratorium her Legislature had passed, saying she would sign a version that exempted one project. Hinojosa will be choosing between those two models, with a Republican president who has already criticized Abbott’s pause.
What to watch
The rest of the count. The lieutenant governor’s race decides who runs the state Senate’s agenda, though the chamber stays Republican; the Texas House, 88–62 Republican going in, decides whether a local veto or labor rules can pass.
December 10 and 17. ERCOT’s audit reports, then the commission’s open meeting on them, with Abbott still governor after conceding. Approvals granted before January 19 are hard to reverse, so what the commission clears in December is largely out of a new governor’s reach.
January 19. Whether Hinojosa signs a moratorium order, what it covers (new projects, or anything not yet switched on) and whether TCEQ and the commission follow it.
December 31. The commission’s deadline for its transmission-cost rule, which as proposed bills large loads on 12 monthly peaks instead of 4 and sets a 20-year minimum bill. The current commission writes it, before Hinojosa takes office.
The exemption bill. Abbott, Hinojosa and both Senate candidates back repeal; grandfathering decides whether it changes the economics of campuses already certified.
Company calls. Oncor and IREN report on November 5, Fermi next week. Watch for Batch Zero commitments, collateral withdrawals and anything self-powered campuses say about permits.
What this is anchored on
Results, filings, permits and statements are as reported; the paths, exposure ratings and the moratorium’s effect are ours.
| Item | Data point | Source |
|---|---|---|
| Results | The AP called the Senate race for Talarico late Tuesday | TIME, Nov 4 |
| Results | CBS News projects Talarico the winner | CBS News, Nov 3 |
| Results | Talarico 59.7%, Paxton 38.8% with about 52% of the expected vote counted (AP count, 9:35 pm ET) | Victoria Advocate (AP data via the Texas Tribune), Nov 3 |
| Results | Hinojosa wins per the AP race call; 57% to 41% with 66.1% of precincts reporting | KPRC Click2Houston, Nov 3 |
| Results | Abbott conceded the governor’s race to Hinojosa | ABC 7 Amarillo, Nov 3 |
| Results | Goodwin declared victory; Patrick had not conceded; the state Senate keeps a Republican majority | Texas Tribune, Nov 3, 10:52 pm CT |
| Results | Early lieutenant governor shares (AP) | KUT, Nov 3 |
| Results | None of the most contested Texas House races called; one Democratic pickup in Corpus Christi | Texas Tribune, Nov 3, 9:23 pm CT |
| Results | Democrats win the Senate majority, CBS News projects | CBS News, Nov 3 |
| Results | Democrats win control of the House and Senate, NBC News projects | NBC News live blog, Nov 3 |
| Abbott | June 10 package for 2027: repeal the sales tax exemption; data centers add generating capacity, pay for interconnection, use water-efficient cooling such as closed loops, report power and water | Texas Tribune, Jun 10 |
| Abbott | Aug 3 directive: PUCT and ERCOT audit every data center in the ERCOT queue; failures denied; more than 474 GW requested, about 90% data centers | Office of the Governor, Aug 3 |
| Abbott | Sep 21 directive: TCEQ to halt data center permits until the audits finish; conditions include covering grid costs, lower residential bills, water and setbacks | Office of the Governor, Sep 21 |
| TCEQ | Paused permits for infrastructure directly supporting data centers; screening pending applications | TCEQ letter to the governor, Oct 19 |
| TCEQ | Air notices, stormwater coverage and generator reviews kept moving after Sep 21 | FracTracker Alliance, Oct |
| TCEQ | TCEQ said permits issued after the order had been suspended, and shut its automatic e-filing system | Texas Public Radio (San Antonio Report), Oct 22 |
| TCEQ | Reads the directive to reach co-located and behind-the-meter generation serving data centers; implies issued permits stand | Bracewell, Sep 23 |
| Abbott, Paxton | Sep 14: Abbott directs the Water Development Board to enforce its water-use survey and refer violators to prosecutors; Sep 24: the attorney general opens an investigation of developers in 18 counties | Willkie Farr & Gallagher, Oct |
| Trump | Called Abbott’s moratorium a mistake; Abbott kept it | CBS Austin, Aug 10 |
| Talarico | Plan: repeal the exemption, large users pay their own grid costs, closed-loop cooling, local approval or rejection, federal minimum standards | Texas Tribune, Jul 22 |
| Paxton | “Texas First” plan: backs Abbott’s state-level proposals and repealing the exemption; own power, closed-loop cooling, limits near rural homes, China ban | Fox 7 Austin, Sep 30 |
| Hinojosa | Executive order halting new data centers until the Legislature passes protections; special session to end the tax breaks | Hinojosa campaign |
| Hinojosa | July 23 call: union labor, local power to reject projects, ban on NDAs hiding water and power use, ratepayer protection, transparency | Hinojosa campaign, citing press |
| Goodwin | Pause new approvals until safeguards; water priority for families and farmers; disclosure; residents’ role in decisions | Galveston County Daily News, Jul 21 |
| Patrick | Interim charges: data centers’ water and power demands and the cost of the sales tax exemption | Texas Tribune, Mar 27 |
| Senate | Democrats need to net four seats to take control of the Senate | CBS News live results, Nov 3 |
| Exemption | At least $1.3B in 2026 (state projections); about $3.2B over the next two years, for 121 data centers (comptroller) | Texas Tribune, Apr 8 |
| PUCT | Johnson appointed Oct 23, 2025 to a term ending Sep 1, 2031 | Office of the Governor, Oct 23, 2025 |
| PUCT | Rhode appointed Mar 12, 2026 to a term ending Sep 1, 2027 | Office of the Governor, Mar 12 |
| PUCT, TCEQ | Senate nominations of May 21, 2025: Gleeson to 2029, Hjaltman to Sep 1, 2025; TCEQ’s Paup to Aug 31, 2027 and Gonzales to 2029 | Texas Senate agenda, May 21, 2025 |
| Constitution | Appointments need two-thirds of senators present; unconfirmed recess appointees are treated as rejected at the end of a regular session | Tex. Const. art. IV §12 (Texas Legal Guide) |
| Constitution | Only the governor who appointed an officer may remove them, with two-thirds of the Senate | Tex. Const. art. XV §9 (Texas Legal Guide) |
| PUCT | Proposed transmission-cost rule: 12CP replaces 4CP; large loads pay a 20-year minimum billing demand; SB 6 deadline Dec 31 | PUCT Project 58000, Jul 9 |
| PUCT | ERCOT and the commission asked the Legislature for direct curtailment and registration authority over large loads | PUCT response to the governor, Jul 17 |
| Elsewhere | New York’s EO 62 pauses permits for data centers of 50 MW or more for about a year; Maine’s governor vetoed a moratorium in April | Built In, Aug 4 |
| Exemption | Senators of both parties questioned it at a Jul 27 hearing; honoring existing certifications left open | Holland & Knight, Jul 30 |
| Enforceability | Former ERCOT market monitor Beth Garza doubts the directive can be enforced without new laws | Texas Public Radio, Aug 5 |
| ERCOT | 17 data center and crypto loads, 6,608 MW, done with every step but approval to energize; a Nov 1 cohort of 17 loads, ~6,874 MW, for Q2 2027; reports Dec 10, PUCT open meeting Dec 17; loads of 25–75 MW not paused | ERCOT presentation to the PUCT, Aug 20 |
| ERCOT | Batch Zero conditional classes: base 66.4 GW (204 projects), studied 125.4–127.9 GW (158), excluded 302.2 GW (373) | ERCOT Board, Item 14, Sep 11 |
| ERCOT | Batch Zero study restarts in December or January; the adjusted load forecast moves to December | ERCOT Board, CEO update, Sep 11 |
| ERCOT | Large loads of all kinds: 9,456 MW approved to energize since 2022; 4,370 MW drawn at July’s peak | ERCOT monthly operational overview, July (Aug 17) |
| ERCOT | Approved large load still 9,456 MW in September | ERCOT monthly operational overview, September (Oct 16) |
| ERCOT | Batch One, for requests outside Batch Zero, targeted to launch in June 2027 | Data Center Frontier, Aug 31 |
| ERCOT | The 2025 forecast method counted new data center requests at 49.8%; average in-service slip about 220 days | ERCOT Board, Item 8.1, Apr 7, 2025 |
| ERCOT | Preliminary 2026 forecast: 39.7 GW of new data center load in 2027 rising to 211.6 GW in 2031, from utility-submitted requests; ERCOT calls it preliminary | ERCOT Board, CEO update, Apr 15 |
| ERCOT | Preliminary all-time peak demand of about 91.1 GW on Jul 22, 2026 | Forbes, Oct 13 |
| PUCT | 16 TAC §25.194 adopted Sep 18: $50,000 per MW of security, a $100,000 initial fee plus tiered study charges, for loads of 75 MW or more | White & Case, Sep 25 |
| Outside view | BNEF: the pause could delay 49.8 GW of data center load; about 8.25 GW of additions in ERCOT through 2030 | POWER, Aug 6 |
| Outside view | CenterPoint expects 3, 8, 11 and 12 GW of Batch Zero load energized in 2027–30; about 2 GW of studied load withdrawn | S&P Global, Oct 27 |
| Outside view | 92 GW of advanced-planning data center load in ERCOT: 11 operating or expanding, 12 under construction, 15 committed | Modo Energy, Oct 21 |
| Curtailment | 525.5 MW of uncompensated emergency curtailment on two Crusoe data centers behind one wind farm (Docket 59220); 933 MW of off-grid gas turbines under construction at the Armstrong County site (no source given) | Global Data Center Hub, Aug 26 |
| Nexus | Anthropic campus, 1.6 GW on-site gas plant; about $15B of financing in talks, with Google guaranteeing Anthropic’s lease and power payments (WSJ’s account) | Global Data Center Hub (WSJ), Aug 3 |
| Nexus | Google agreed to guarantee the senior debt; $1.3B mezzanine loan closed; final investment decision reached | The Next Web (Bloomberg), Aug 20 |
| Nexus, Frontier | Major-source air permit notices mailed Sep 22 for Nexus Hubbard and VoltaGrid’s Frontier plant | Public Citizen permit summary |
| Nexus | State building filings: HB1 to Oct 2027, HB2 to Jan 2028 | DCD |
| Frontier | 1.4 GW of critical IT in 10 buildings; first building 2H 2026 | Vantage Data Centers |
| Frontier | About 700 MW from 210 gas engines, approved by TCEQ per filings | Construction Owners (Business Insider), Oct 24, 2025 |
| Frontier | Projected building dates Aug 2027 to Nov 2028 (estimate) | Epoch AI |
| Abilene | 900 MW campus for Microsoft with its own power plant; first building mid-2027; the 1.2 GW Stargate campus complete by end-2026 | Crusoe, Mar 27 |
| Abilene | PSD application by Crusoe for added generation at the Longhorn data center, under technical review; the link to Microsoft’s expansion is ours | TCEQ notice 182126 |
| Kilby | 20-year power agreement with Microsoft; about 2.67 GW of gas; FID by end-2026; first power 2028 | Chevron, Jun 22 |
| Kilby | Islanded campus, about 2 GW of data centers over 5–7 years | Global Data Center Hub, Jun 29 |
| Kilby | Only a minor-source permit-by-rule application found at TCEQ | Public Citizen permit summary |
| Cameron | Fluidstack, up to 1.5 GW with on-site generation; phase 1 mid-2028 | The Energy Mag, Sep 22 |
| Milam | OpenAI 1.2 GW lease; SB Energy builds new generation | OpenAI, Jan 9 |
| Childress | Crusoe and Lancium 1 GW campus; construction Q3 2026 | Crusoe, Jul 15 |
| Childress | Meta contracts about 1.6 GW from Crusoe across Childress and Missouri (reported) | DCD (Bloomberg) |
| Google, Amazon | Campus power capacities (Armstrong ~1,065 MW, Wilbarger ~850 MW, Meitner ~840 MW); secondary | Cleanview |
| Comanche Peak | 1.2 GW nuclear PPA for Amazon; energize 2027; Vistra says the pause doesn’t affect it | Utility Dive, Aug 10 |
| GW Ranch | 7.65 GW gas air permit issued; phase 1 of 1 GW with first power H1 2027 | Pacifico Energy (BusinessWire), Jan 26 |
| GW Ranch | Amazon acquired the site in August (secondary) | Let’s Data Science, Aug 8 |
| El Paso | El Paso Electric’s 366 MW McCloud plant for Meta; judges recommend approval only if Meta bears the cost | Inside Climate News, Sep 24 |
| Helios | Base and studied classifications for Helios I–II and 2.6 GW of other sites | Galaxy, Sep 8 |
| Helios | Phase II deliveries from Q2 2027; Helios II without a tenant; TCEQ freeze not expected to affect timelines | BigGo Finance (Galaxy Q3 call), Oct 27 |
| Cipher | Colchis 1 GW base load; 1.6 GW studied; laterals for up to 2.5 GW of on-site generation | Cipher Digital, Nov 2 |
| Cipher | Barber Lake lease extended to 20 years, about $9.1B | Cipher Digital, Nov 2 |
| IREN | 2 GW Sweetwater hub included as Batch Zero base load | IREN, Sep 8 |
| IREN | Horizon 1 delivered to Microsoft at Childress | IREN FY26 results, Aug 27 |
| Riot, Hut 8 | Rockdale 191 MW IT for an AI lab; Beacon Point 704 MW IT leased (secondary ledger citing company releases) | Regards of Wall Street |
| Fermi | TensorWave lease not effective after the Oct 31 closing date passed | Fermi (via StockTitan), Nov 3 |
| Fermi | About 2 GW targeted by end-2027; a further ~5 GW air permit filed Mar 27 | Converge Digest (Fermi 10-K), Mar 30 |
| Horizon | CoreWeave’s deal with Poolside fell apart | Baxtel (Financial Times), Apr 4 |
| Sailfish | Hood County rejected the Comanche Circle settlement and permit appeal | Texas Public Radio, Oct 13 |
| San Antonio | Notice of intent to sue Vantage and VoltaGrid over off-grid permits | Baxtel, Jul 24 |
Method
What the paths count. New data center load switched on in Texas after September 2026, at quarter-ends through 2030, in five parts. ERCOT’s 17 cleared loads enter at 6.9 GW, the size of its November cohort of 17 loads, which we take to be the same ones, at their full requested peak; ERCOT gives that peak over five years, and we ramp it evenly. Batch Zero’s base load, 66.4 GW, is cut to the 49.8% realization rate of ERCOT’s 2025 forecast method, less the cleared loads, which we assume are part of it (26.2 GW), and ramps evenly from July 2027 to December 2032. Named self-powered campuses with permits pending (Nexus, Frontier’s second half, Abilene for Microsoft, Pecos) and with permits issued (Frontier’s first half, GW Ranch’s first phase, Meitner, the San Antonio pair) follow their announced or estimated dates, and the campuses outside ERCOT (El Paso, Abernathy) theirs. Batch Zero’s studied load (allocations from 2028, pending a study that hasn’t restarted) and the excluded 302 GW (waiting for Batch One) aren’t in the paths; we judge neither likely to arrive in volume before 2029. Fluidstack’s Cameron County site isn’t modeled separately: its grid request is in ERCOT’s queue, probably mostly in studied load.
Before the freeze. The cleared loads start in December 2026, base load in July 2027, and every named campus on its own date. Abbott’s path moves the cleared loads to Q2 2027, when ERCOT slates its November cohort, base load by three months, and permits pending on September 21 by the 4.3 months to the end of January.
Hinojosa’s path. A moratorium on new data centers runs from inauguration to the date picked (June 20, September 1 or December 31, 2027). It reaches 75% of base load, all pending own-gas permits and a quarter of the issued-permit and out-of-ERCOT campuses; it reaches the cleared loads only if the commission hasn’t approved them before January 19, which we put at even odds, and then half of them. Because the agencies are run by Abbott appointees and an order can be challenged, only part of the moratorium holds: 60% with Hinojosa alone, 80% with the lieutenant governor too and 90% with the Texas House as well. Each part’s schedule moves later by the share that holds times the months between the end of January and the moratorium’s end. Cancellations take a share of what each part adds after inauguration, across the three outcomes: 3–8% of base load, 10–20% of pending own-gas campuses, 3–8% of issued-permit campuses and 2–5% of those outside ERCOT, for local vetoes, a tax repeal without grandfathering and developers moving elsewhere. All of these are judgments, not data. The pace matters most: at a 25% realization of base load the base-case gap at the end of 2028 is 2.0 GW, at 100% it is 4.6 GW. Our Abbott path, about 30 GW of new data center load by 2030, is well above BNEF’s outlook of about 8 GW of additions in ERCOT through 2030; CenterPoint alone expects 12 GW of Batch Zero load of all kinds switched on in its territory by 2030.
Exposure ratings are ours: high where a tenant-backed campus waits on a TCEQ air permit for power due in 2027–28; medium where it waits on an ERCOT switch-on, a commission vote or a contested permit; low where it is switched on or holds its approvals; company risk where its own financing or tenant, not the state, sets its timing. Results are unofficial counts and race calls as reported, with the time of each.