Analysis · Power & politics

020What does a blue Texas mean for the data center boom?

Democrats won Texas’s races for governor and US Senate on Tuesday: the AP called both for Gina Hinojosa and James Talarico, and Gov. Greg Abbott conceded. The freeze came first: since August, Abbott’s audit has held every large data center (75 MW or more) waiting to switch on in ERCOT, and since September his order to the state’s environmental agency has been read to cover the permits for the gas plants that let campuses skip the queue. In our base case Hinojosa leaves Texas with about 2.2 GW less new data center load switched on at the end of 2027 than Abbott’s path would have, and 2.9 GW less at the end of 2028 (2.0–5.9 GW, depending on the races still being counted and how long a moratorium lasts). That is on top of the roughly 2.2 GW Abbott’s freeze already costs at each date. About half the gap is grid load in ERCOT’s Batch Zero arriving later; per GW, the hardest hit are self-powered campuses for Microsoft, Anthropic and OpenAI whose air permits are pending or still to come.

Requested from ERCOT
474 GW
About 90% data centers. Batch Zero’s preliminary sort set aside 302 GW for a later round
Cleared, frozen since Aug 3
6.6 GW
17 loads done with every step but the switch-on. Batch Zero’s base and studied groups hold 194 GW
Less switched on, end of 2028
2.9 GW
Hinojosa vs Abbott’s path, base case. Range 2.0–5.9 GW
Most exposed
6.7 GW
Self-powered campuses whose air permits are pending or still to come: Microsoft, Anthropic, OpenAI and Oracle, Fluidstack. Plant and IT capacity as reported

The results so far

As reported late on Nov 3. Calls are the AP’s unless noted; shares are from the time shown in each row and will move as counting finishes.

US Senate
James Talarico✓59.7%
Ken Paxton38.8%
Called for Talarico by the AP late Tuesday; CBS and NBC also projected him. Shares are the AP count at about 52%, 9:35 pm ET
Governor
Gina Hinojosa✓~57%
Greg Abbott~41%
Called for Hinojosa by the AP; Abbott conceded. Shares at 66% of precincts, 11:03 pm ET (KPRC)
Lieutenant governor
Vikki Goodwin~59%
Dan Patrick~40%
No call we could confirm as of 11:52 pm ET; Goodwin declared victory and Patrick had not conceded (Texas Tribune). Shares from early returns
Texas House
Control not called as of 10:23 pm ET; 88–62 Republican going in. The state Senate keeps a Republican majority (Texas Tribune)

Texas froze its own boom

Hinojosa inherits a pipeline her Republican predecessor had already stopped. On August 3, Gov. Greg Abbott told the Public Utility Commission and ERCOT to audit every data center seeking a grid connection and to deny any that failed. ERCOT stopped approving data centers of 75 MW or more to switch on. Seventeen loads, about 6.6 GW, had cleared every step but that one; none has been approved since. ERCOT slates a cohort of 17 loads, which we take to be the same ones, for the second quarter of 2027. ERCOT also halted Batch Zero, the first round of its new process for large loads, which holds 194 GW in its base and studied groups.

On September 21 the freeze reached the workaround. Abbott told the Texas Commission on Environmental Quality to stop issuing permits for data centers until the audits finish, and law firms read that to include the on-site gas plants that let a campus skip ERCOT’s queue, but not permits already issued. Enforcement has been leaky: watchdogs counted air notices and stormwater approvals after the order; TCEQ later said the permits issued since then had been suspended, and shut its automatic e-filing system. Abbott kept the pause after President Trump called it a mistake. ERCOT files its audit on December 10, and the commission takes it up on December 17, five weeks before Hinojosa is sworn in.

The freeze came first

Official actions and campaign plans on data centers in 2026, and the dates that decide what replaces the freeze.

State governmentLegislatureCandidatesWashingtonScheduled
  1. Patrick’s interim chargesSenate committees told to study data centers’ water and power demands and the cost of their sales tax exemption
  2. Abbott’s data center packageAsks the 2027 Legislature to repeal the sales tax exemption and make data centers add generating capacity, pay for their own interconnection, use water-efficient cooling such as closed loops and report power and water use
  3. Talarico’s planRepeal the sales tax exemption, make large users pay for their own grid costs, closed-loop cooling, local approval or rejection, federal minimum standards
  4. Hinojosa calls for a moratoriumAsks Abbott to halt new data centers by executive order until the Legislature passes protections
  5. Senate Finance hearingSenators from both parties question the sales tax exemption; whether existing certifications would be honored is left open
  6. ERCOT audit and pauseAbbott directs the PUCT and ERCOT to audit every data center in the queue before approving more; ERCOT postpones its Batch Zero study
  7. Trump calls the pause a mistakeIn an interview reported Aug 9–10; Abbott keeps it
  8. Water reporting enforcedAbbott directs the Texas Water Development Board to enforce its water-use survey and refer data centers that skip it to prosecutors
  9. PUCT large-load ruleLoads of 75 MW or more post $50,000 per MW of security and pay a $100,000 initial fee plus study charges
  10. TCEQ permits haltedAbbott tells TCEQ to stop issuing permits for data centers until the ERCOT and water audits finish; law firms read the halt to reach on-site gas plants
  11. Attorney general opens an inquiryInto developers in 18 counties that skipped the state’s water survey
  12. Paxton’s plan reportedBacks Abbott’s state-level proposals and repealing the exemption; own power, closed-loop cooling, a China ban

Most of the rulebook is already agreed

Abbott’s June package, Paxton’s Senate plan and the Democrats’ plans overlap more than the campaigns suggest. Abbott, Paxton, Talarico and Hinojosa would all repeal the data center sales tax exemption, which state projections put at $1.3 billion or more in 2026 (the comptroller counts 121 data centers using it). Abbott, Paxton and Talarico would also make data centers pay for their own power and grid connections, and Hinojosa would protect households from rate increases driven by data centers. Senators of both parties questioned the exemption at a July hearing; whether existing certifications would be honored was left open. Both sides’ plans put those rules before the 2027 session.

What Democrats add is narrower: a moratorium until laws pass (Hinojosa by executive order, Goodwin through a special session), a local veto over projects (Talarico, Hinojosa; Goodwin wants residents consulted), union labor on construction (Hinojosa) and, from the Senate seat, federal minimum standards (Talarico).

Both parties want most of the same rules

What each statewide candidate proposed for data centers, or did in office, as reported through October. proposed or did it · partly, or a narrower version.

AbbottR · GovernorHinojosaD · GovernorPaxtonR · US SenateTalaricoD · US SenatePatrickR · Lt. governorGoodwinD · Lt. governor
Repeal the data center sales tax exemptionPatrick ordered a Senate study of its cost; Goodwin attacks the incentives and wants a special session on costs. Neither has said “repeal” in coverage we found
Data centers pay for their own power and grid connectionHinojosa would protect households from rate increases driven by data centers; Goodwin opposes households paying for grid buildout
Closed-loop cooling or water priority for residentsHinojosa’s plan targets nondisclosure of water use rather than cooling design; Patrick ordered a study of data centers’ water demands
Disclose power and water useAs attorney general, Paxton opened an inquiry into developers that skipped the state’s water survey. Talarico would publish records of data centers’ tax breaks and include transparency in federal minimum standards; his plan as reported has no power or water reporting
Pause new approvalsAbbott’s pause runs until the audits finish; Hinojosa’s and Goodwin’s until the Legislature passes protections. Paxton backs Abbott’s state-level proposals but hasn’t addressed the pause in coverage we found
Local power to approve or reject projectsAbbott requires setbacks; Paxton backs limits near rural homes and rules on noise and lighting; Goodwin wants nearby residents consulted. None of the three proposes a local veto
Licensed, union labor on construction
Federal minimum standards for data centers
Ban Chinese technology in data centers

What Hinojosa can actually do

Less than the campaign suggests in 2027, and more by 2028. A governor can’t write statute: the session that opens January 12 needs the Legislature, and the Texas House went into the election 88–62 Republican. Her levers are directives and appointments. Abbott’s freeze is a set of letters, which a successor can keep, rewrite or rescind, but the agencies’ commissioners decide how to act on them, and she can’t remove the ones Abbott appointed: only the governor who made an appointment can, with two-thirds of the state Senate.

The utility commission turns over faster than that suggests. A new governor can name its chair as soon as she takes office. Two of its five commissioners appear to be Abbott recess appointees who need two-thirds of the Senate by May 31 or lose their seats, a third appears to be serving past an expired term, and two terms end on September 1, 2027. Recess appointments after the session could give Hinojosa a majority of the commission by late 2027 without a Senate vote, on one reading of the constitution that hasn’t been tested. That matters less for the 2027 freeze than for the rules that follow it: Batch Zero’s allocations, the next batch and who pays for transmission. At TCEQ, one of three seats turns over in August 2027.

How far a letter goes is already in question. ERCOT and the commission complied with Abbott’s, yet a former ERCOT market monitor doubts its requirements can be enforced without new laws, and both agencies asked lawmakers for more authority. A successor’s order would meet the same doubt, from agencies she didn’t appoint, and probably a lawsuit. That is why our paths assume only part of a Democratic moratorium holds, and more of it the more offices Democrats win.

Most of the queue was never coming

ERCOT’s large-load pipeline by stage, from its September Batch Zero classification and monthly reports, with the named self-powered campuses whose permits are pending. ERCOT’s stages are separate counts on different dates, so they don’t add up to a total.

Data
StageGWProjectsWhat it means
Switched on since 20229.5—Large loads of all kinds (data centers, crypto, industrial and others) ERCOT has approved to energize since 2022; 4.4 GW drawn at July’s peak. Unchanged through September.
Cleared, waiting to switch on6.617Finished every ERCOT step except approval to energize (Aug 20). ERCOT’s Nov 1 cohort, also 17 loads (about 6.9 GW), is slated for Q2 2027; we assume they are the same loads. None approved since Aug 3.
Batch Zero base load66.4204All required ERCOT studies approved; modeled as given. Conditional on the audit.
Batch Zero, to be studied127.9158A qualifying study submitted; each gets a 2028–32 allocation, possibly zero. ERCOT’s slides give 125.4–127.9 GW.
Excluded, to Batch One302.2373No qualifying study or dynamic model by Jul 10; deferred to Batch One, which ERCOT targets to launch in June 2027. Preliminary until the audit.
Own gas, permit pending6.7—Named self-powered campuses whose air permits were pending on Sep 21 (Nexus for Anthropic, Frontier for OpenAI and Oracle, Microsoft’s Abilene expansion by our attribution) or that will need them (Microsoft’s Pecos campus, Fluidstack’s Cameron County site). Mixes plant and IT capacity as each project reports it.

The 474 GW is a list of requests, not a pipeline: more than five times ERCOT’s record peak of about 91 GW. ERCOT’s 2025 forecasting method counted new data center requests at 49.8%, and only about 46% of the large load it has approved since 2022 showed up at July’s peak. So the freeze matters less for the headline number than for the few dozen GW with studies, tenants and money behind them. We model those: the cleared loads, Batch Zero’s base load at ERCOT’s 49.8% realization, and the named self-powered and out-of-ERCOT campuses. That puts about 17.2 GW of new data center load on before the end of 2028 had nothing been frozen, and 14.9 GW on Abbott’s path.

What Hinojosa adds to the delay

New data center load switched on in Texas after September 2026, GW, before the freeze, on the path Abbott had set and under Hinojosa. Pick which other races Democrats win and when a moratorium ends; the base case is Hinojosa alone, with a Republican lieutenant governor and House, and a moratorium that ends in September 2027.

About 2.2 GW less switched on by the end of 2027 than on Abbott’s path and 2.9 GW less by the end of 2028; about 1.0 GW never built by 2030. Grid approvals wait about 3 months longer, own-gas permits about 4 months.

Before the freezeAbbott’s pathHinojosa
Data
Quarter endBefore the freezeAbbott’s pathHinojosa+ Goodwin+ Texas House
Sep 30, 20260.00.00.00.00.0
Dec 31, 20260.40.20.20.10.1
Mar 31, 20271.41.00.70.60.5
Jun 30, 20273.22.31.81.61.5
Sep 30, 20275.53.32.72.62.5
Dec 31, 20278.05.83.73.53.3
Mar 31, 202810.38.05.95.14.7
Jun 30, 202813.010.38.07.26.7
Sep 30, 202815.112.610.09.28.7
Dec 31, 202817.214.912.111.110.5
Mar 31, 202919.117.014.513.412.6
Jun 30, 202921.018.916.415.514.7
Sep 30, 202922.920.818.417.416.6
Dec 31, 202924.822.820.219.218.4
Mar 31, 203026.524.622.021.020.1
Jun 30, 203028.126.323.722.721.7
Sep 30, 203029.827.925.424.323.4
Dec 31, 203031.429.627.126.025.0

Democratic columns use a moratorium that ends in September 2027.

On Abbott’s path the commission acts on the audit in December, switch-ons and permits resume early in 2027, and the 2027 session writes his package into law. Texas adds about 5.8 GW of new data center load by the end of 2027 and 14.9 GW by the end of 2028. With Hinojosa sworn in on January 19, a moratorium on new data centers runs until the Legislature passes protections she signs. In the base case approvals wait about 3 months longer and own-gas permits about 4, which leaves Texas 2.2 GW short at the end of 2027 and 2.9 GW short at the end of 2028, with about 1.0 GW never built by 2030. If Goodwin’s lead for lieutenant governor holds, the gap at the end of 2028 is about 3.8 GW.

The range runs from 2.0 GW at the end of 2028, if the moratorium ends when the session does, to 5.9 GW if Democrats also win the lieutenant governor’s office and the Texas House and the moratorium lasts to the end of 2027. Most of the gap is time, not cancellations: the GW come later. The hardest hit are self-powered campuses, where the governor’s environmental agency is the gate: on Abbott’s path about 2.8 GW of them is running by the end of 2028; in the base case, 1.6 GW.

Whose campuses carry the risk

Texas capacity by company, split by what it is waiting on; Batch Zero base load, whose required studies are approved, counts as approved. GW are near-term phases as each project reports them (IT, facility or on-site generation), so the bars compare exposure, not exact load. Hover or tap a bar for the projects.

On or energizingApproved, waiting or buildingIn ERCOT’s queueOwn gas, permit pendingOwn gas, permit issuedOutside ERCOT

Self-powered campuses are the most exposed

The irony of the freeze is that the campuses built to avoid the grid are the ones a governor reaches most directly. ERCOT’s pause runs through a utility commission whose members a new governor can replace only as their seats come open; TCEQ’s permits are where a governor’s letter has already worked. Five campuses were waiting on air permits, or will need them:

  • Anthropic’s Hill County campus (Nexus): a 1.6 GW gas plant, with about $15 billion of senior debt that Google agreed to guarantee, per Bloomberg; its major-source permit drew a hearing request in October.
  • Microsoft’s 900 MW Abilene expansion with Crusoe, first building due mid-2027, where a pending permit for added generation appears to cover its plant (our reading of a TCEQ notice that names Crusoe), and its Pecos campus with Chevron, about 2 GW from 2028, where a minor-source authorization is in review and we found no filing yet for the main air permit.
  • OpenAI and Oracle’s Frontier in Shackelford County, where VoltaGrid’s major-source air permit for the site is pending; its first engines were approved in 2025.
  • Fluidstack’s Cameron County site, up to 1.5 GW with on-site generation that will need permits, in the county with the most Batch Zero base and studied load; its tenant isn’t named.

Grid-tied campuses carry timing risk, not existential risk. Some hold ERCOT approvals or base-load status: Galaxy’s Helios for CoreWeave, IREN’s Sweetwater, Cipher’s Colchis and Crusoe’s Childress site for Meta. Others’ ERCOT status isn’t public: Cipher’s Barber Lake, Google’s Armstrong and Wilbarger campuses and Amazon’s Comanche Peak site, which Vistra says the pause doesn’t affect. Most of their dates hinge on December 17. Amazon’s GW Ranch already holds its 7.65 GW air permit, which makes it one of the least exposed large projects in the state. Fermi’s risk is its own: its only announced lease isn’t in force.

A longer freeze also has winners. Every megawatt already energized in Texas becomes scarcer: IREN’s Childress site, Cipher’s Black Pearl for AWS and Core Scientific’s Denton campus could command better terms on new or renewed contracts as new supply slips, and capacity outside Texas gets a political-risk premium it didn’t have a year ago.

The projects

Named Texas campuses of about 200 MW or more, what each is waiting on and our read of its exposure to Hinojosa relative to the path Abbott had set. Capacity is as each project reports it.

ProjectWhoCapacityPowerWaiting onExposure
Nexus HubbardHill CountyNexus; Anthropic tenant; Google agreed to guarantee about $15B of senior debt (Bloomberg)GOOGL1.6 GW gas plant (build-out 6–8 GW)ERCOT area, own gas plantMajor-source air permit: comments closed Oct 23, hearing requested; pausedHigh
Frontier (Stargate)Shackelford CountyVantage, VoltaGrid; Oracle for OpenAIORCL1.4 GW ITOff-grid gasVoltaGrid major-source air permit (notice Sep 22) paused; first engines approved in 2025High
Abilene expansion (Microsoft)Taylor CountyCrusoe; MicrosoftMSFT0.9 GW (672 MW IT)Own 900 MW plantPSD air permit for added generation under review, paused (our attribution)High
Pecos campus and Project KilbyReeves CountyChevron, Engine No. 1; Microsoft 20-year PPAMSFT, CVX~2 GW DC (2.67 GW gas)Islanded gasFinal investment decision by end-2026; a minor-source authorization in review, no main air permit filing foundHigh
Cameron County campusCameron CountyFluidstack; tenant not namedUp to 1.5 GWERCOT plus own generationERCOT switch-on and permits for on-site generation; no permit filing foundMedium
Milam County (Stargate)Milam CountySB Energy (SoftBank); OpenAI 1.2 GW lease9984.T1.2 GWERCOT plus new generationERCOT switch-on (inferred); building 1 was due Oct 2026Medium
Childress “Project Hyper”Childress CountyCrusoe, Lancium; Meta (reported)META1.0 GWERCOT1 GW interconnection approved; switch-ons after the auditMedium
Armstrong County (Goodnight)Armstrong CountyCrusoe; GoogleGOOGL~1.07 GW (secondary)ERCOT plus co-located wind and on-site gasSwitch-ons for buildings due 2027–28; a 525 MW curtailment obligation behind one wind farm; 933 MW of on-site gas turbines reported under construction (secondary)Medium
Wilbarger County “Project Rise”Wilbarger CountyGoogleGOOGL~0.85 GW (secondary)ERCOT plus AES generationSwitch-on (likely in the paused group)Medium
Comanche Peak campusSomervell CountyAmazon; Vistra 20-year PPAAMZN, VST1.2 GW PPAERCOT, nuclear PPAEnergize 2027; Vistra says the pause doesn’t affect itMedium
HeliosDickens CountyGalaxy; CoreWeave leases Phases I–IIIGLXY, CRWV1.6 GW approved; 2.6 GW more in studyERCOTPhase II (260 MW IT) from Q2 2027 and Helios II (830 MW, no tenant) need switch-ons; 2.6 GW in studyMedium
Barber LakeMitchell CountyCipher; Fluidstack with a Google backstop, then an AI labCIFR, GOOGL0.3 GW (207 MW IT)ERCOTHalls due Q4 2026–Q1 2027 need switch-onsMedium
Colchis and Cipher’s other sitesWest TexasCipher; no tenant namedCIFR1 GW base + 1.6 GW in studyERCOT (AEP)Batch Zero base load (Colchis, 2028) and studied load; plans for up to 2.5 GW of on-site gas would need TCEQMedium
SweetwaterNolan CountyIREN; no tenant namedIREN2 GW (1.4 GW substation energized)ERCOTBatch Zero base load awaiting verification; first 300 MW due Q4 2027Medium
Beacon PointNueces CountyHut 8; investment-grade tenant not named (704 MW IT leased)HUT1 GW campusERCOTBatch Zero base load (secondary source); phase 1 timing undisclosed, phase 2’s first hall Q2 2028Medium
El Paso campusEl Paso CountyMeta; El Paso Electric’s 366 MW McCloud plantMETA~1 GWWECC (El Paso Electric)PUCT vote on McCloud; judges back it only if Meta bears the costMedium
San Antonio off-grid pairBexar CountyVantage, VoltaGrid; tenant not named0.42 GW gasOff-grid gasMinor-source permits issued; notice of intent to sue over source splittingMedium
CloudBurst San MarcosGuadalupe CountyCloudBurst; tenant not namedET1.2 GWERCOT area, Energy Transfer gasGrid or own-gas approvals, mix not disclosedMedium
Caldwell ValleyCaldwell CountyTract; tenant not namedUp to 4 GW; 360 MW firstERCOTLater ERCOT batches; a gas plant would need TCEQMedium
Stargate AbileneTaylor CountyCrusoe, Lancium; Oracle for OpenAIORCL1.2 GWERCOTLast buildings due by end-2026; a turbine amendment is pausedLow
GW RanchPecos CountyAmazon; Pacifico EnergyAMZN1 GW phase 1 (7.65 GW gas permitted)Off-grid gas, grid laterAir permit issued Jan 2026; a later grid tie would be exposedLow
Childress (Horizon)Childress CountyIREN; Microsoft $9.7B contract, Nvidia $3.4BIREN, MSFT0.75 GW grid connectionERCOTEnergized site; AI halls through 2027Low
Black Pearl and StingrayWinkler and Andrews countiesCipher; AWS leasesCIFR, AMZN0.3 GW + 0.1 GWERCOTBlack Pearl energized and ramping; Stingray’s shell due in Q4 (Cipher)Low
RockdaleMilam CountyRiot; Anthropic (per Bloomberg) 20-year leaseRIOT191 MW ITERCOTBuilt on an energized mining site; 96 MW Dec 2027, 95 MW Jun 2028 (secondary)Low
DentonDenton CountyCore Scientific; CoreWeaveCORZ, CRWV~0.36 GWERCOTOperatingLow
MeitnerGray and Roberts countiesGoogle, IntersectGOOGL~0.84 GW (secondary)Panhandle, own gas firmingGas permit appears issued in MayLow
Project MatadorCarson CountyFermi; TensorWave lease not yet effectiveFRMI, AMD2 GW target by end-2027 (11 GW plan)SPP plus own gasLease financing; a further 5 GW air permit was filed in March, status not foundCompany risk
Project HorizonPecos CountyPoolside; CoreWeave exitedCRWV2 GWOwn gas (planned)No anchor tenant since AprilStalled
Comanche CircleHood CountySailfish; no tenantUp to 5 GWERCOT plus planned gasCounty rejected its settlement Oct 13; NRG withdrew the gas plantStalled

The Senate seat matters less, for now

Democrats needed a net gain of four seats for a Senate majority, and NBC and CBS project they got it, with Talarico’s seat among the gains; NBC also projects a Democratic House. Even with both chambers, bills face a Republican president’s veto until 2029, so Talarico’s federal minimum standards for data centers are a long shot. What changes sooner is confirmations, including FERC and NRC commissioners, and the ability to block a federal bill preempting state AI or data center rules.

ERCOT sits largely outside FERC’s wholesale jurisdiction, so Washington’s reach into the Texas buildout runs mainly through much of the Panhandle and El Paso, which belong to the SPP and WECC grids. For the campuses in this pack the governor matters far more than the senator.

Democratic governors have gone both ways

Facing the same backlash, two Democratic governors made opposite calls this year. In July, New York’s Kathy Hochul ordered a pause on new permits for data centers of 50 MW or more, for about a year while the state writes an environmental review process. In April, Maine’s Janet Mills vetoed a moratorium her Legislature had passed, saying she would sign a version that exempted one project. Hinojosa will be choosing between those two models, with a Republican president who has already criticized Abbott’s pause.

What to watch

The rest of the count. The lieutenant governor’s race decides who runs the state Senate’s agenda, though the chamber stays Republican; the Texas House, 88–62 Republican going in, decides whether a local veto or labor rules can pass.

December 10 and 17. ERCOT’s audit reports, then the commission’s open meeting on them, with Abbott still governor after conceding. Approvals granted before January 19 are hard to reverse, so what the commission clears in December is largely out of a new governor’s reach.

January 19. Whether Hinojosa signs a moratorium order, what it covers (new projects, or anything not yet switched on) and whether TCEQ and the commission follow it.

December 31. The commission’s deadline for its transmission-cost rule, which as proposed bills large loads on 12 monthly peaks instead of 4 and sets a 20-year minimum bill. The current commission writes it, before Hinojosa takes office.

The exemption bill. Abbott, Hinojosa and both Senate candidates back repeal; grandfathering decides whether it changes the economics of campuses already certified.

Company calls. Oncor and IREN report on November 5, Fermi next week. Watch for Batch Zero commitments, collateral withdrawals and anything self-powered campuses say about permits.

What this is anchored on

Results, filings, permits and statements are as reported; the paths, exposure ratings and the moratorium’s effect are ours.

ItemData pointSource
ResultsThe AP called the Senate race for Talarico late TuesdayTIME, Nov 4
ResultsCBS News projects Talarico the winnerCBS News, Nov 3
ResultsTalarico 59.7%, Paxton 38.8% with about 52% of the expected vote counted (AP count, 9:35 pm ET)Victoria Advocate (AP data via the Texas Tribune), Nov 3
ResultsHinojosa wins per the AP race call; 57% to 41% with 66.1% of precincts reportingKPRC Click2Houston, Nov 3
ResultsAbbott conceded the governor’s race to HinojosaABC 7 Amarillo, Nov 3
ResultsGoodwin declared victory; Patrick had not conceded; the state Senate keeps a Republican majorityTexas Tribune, Nov 3, 10:52 pm CT
ResultsEarly lieutenant governor shares (AP)KUT, Nov 3
ResultsNone of the most contested Texas House races called; one Democratic pickup in Corpus ChristiTexas Tribune, Nov 3, 9:23 pm CT
ResultsDemocrats win the Senate majority, CBS News projectsCBS News, Nov 3
ResultsDemocrats win control of the House and Senate, NBC News projectsNBC News live blog, Nov 3
AbbottJune 10 package for 2027: repeal the sales tax exemption; data centers add generating capacity, pay for interconnection, use water-efficient cooling such as closed loops, report power and waterTexas Tribune, Jun 10
AbbottAug 3 directive: PUCT and ERCOT audit every data center in the ERCOT queue; failures denied; more than 474 GW requested, about 90% data centersOffice of the Governor, Aug 3
AbbottSep 21 directive: TCEQ to halt data center permits until the audits finish; conditions include covering grid costs, lower residential bills, water and setbacksOffice of the Governor, Sep 21
TCEQPaused permits for infrastructure directly supporting data centers; screening pending applicationsTCEQ letter to the governor, Oct 19
TCEQAir notices, stormwater coverage and generator reviews kept moving after Sep 21FracTracker Alliance, Oct
TCEQTCEQ said permits issued after the order had been suspended, and shut its automatic e-filing systemTexas Public Radio (San Antonio Report), Oct 22
TCEQReads the directive to reach co-located and behind-the-meter generation serving data centers; implies issued permits standBracewell, Sep 23
Abbott, PaxtonSep 14: Abbott directs the Water Development Board to enforce its water-use survey and refer violators to prosecutors; Sep 24: the attorney general opens an investigation of developers in 18 countiesWillkie Farr & Gallagher, Oct
TrumpCalled Abbott’s moratorium a mistake; Abbott kept itCBS Austin, Aug 10
TalaricoPlan: repeal the exemption, large users pay their own grid costs, closed-loop cooling, local approval or rejection, federal minimum standardsTexas Tribune, Jul 22
Paxton“Texas First” plan: backs Abbott’s state-level proposals and repealing the exemption; own power, closed-loop cooling, limits near rural homes, China banFox 7 Austin, Sep 30
HinojosaExecutive order halting new data centers until the Legislature passes protections; special session to end the tax breaksHinojosa campaign
HinojosaJuly 23 call: union labor, local power to reject projects, ban on NDAs hiding water and power use, ratepayer protection, transparencyHinojosa campaign, citing press
GoodwinPause new approvals until safeguards; water priority for families and farmers; disclosure; residents’ role in decisionsGalveston County Daily News, Jul 21
PatrickInterim charges: data centers’ water and power demands and the cost of the sales tax exemptionTexas Tribune, Mar 27
SenateDemocrats need to net four seats to take control of the SenateCBS News live results, Nov 3
ExemptionAt least $1.3B in 2026 (state projections); about $3.2B over the next two years, for 121 data centers (comptroller)Texas Tribune, Apr 8
PUCTJohnson appointed Oct 23, 2025 to a term ending Sep 1, 2031Office of the Governor, Oct 23, 2025
PUCTRhode appointed Mar 12, 2026 to a term ending Sep 1, 2027Office of the Governor, Mar 12
PUCT, TCEQSenate nominations of May 21, 2025: Gleeson to 2029, Hjaltman to Sep 1, 2025; TCEQ’s Paup to Aug 31, 2027 and Gonzales to 2029Texas Senate agenda, May 21, 2025
ConstitutionAppointments need two-thirds of senators present; unconfirmed recess appointees are treated as rejected at the end of a regular sessionTex. Const. art. IV §12 (Texas Legal Guide)
ConstitutionOnly the governor who appointed an officer may remove them, with two-thirds of the SenateTex. Const. art. XV §9 (Texas Legal Guide)
PUCTProposed transmission-cost rule: 12CP replaces 4CP; large loads pay a 20-year minimum billing demand; SB 6 deadline Dec 31PUCT Project 58000, Jul 9
PUCTERCOT and the commission asked the Legislature for direct curtailment and registration authority over large loadsPUCT response to the governor, Jul 17
ElsewhereNew York’s EO 62 pauses permits for data centers of 50 MW or more for about a year; Maine’s governor vetoed a moratorium in AprilBuilt In, Aug 4
ExemptionSenators of both parties questioned it at a Jul 27 hearing; honoring existing certifications left openHolland & Knight, Jul 30
EnforceabilityFormer ERCOT market monitor Beth Garza doubts the directive can be enforced without new lawsTexas Public Radio, Aug 5
ERCOT17 data center and crypto loads, 6,608 MW, done with every step but approval to energize; a Nov 1 cohort of 17 loads, ~6,874 MW, for Q2 2027; reports Dec 10, PUCT open meeting Dec 17; loads of 25–75 MW not pausedERCOT presentation to the PUCT, Aug 20
ERCOTBatch Zero conditional classes: base 66.4 GW (204 projects), studied 125.4–127.9 GW (158), excluded 302.2 GW (373)ERCOT Board, Item 14, Sep 11
ERCOTBatch Zero study restarts in December or January; the adjusted load forecast moves to DecemberERCOT Board, CEO update, Sep 11
ERCOTLarge loads of all kinds: 9,456 MW approved to energize since 2022; 4,370 MW drawn at July’s peakERCOT monthly operational overview, July (Aug 17)
ERCOTApproved large load still 9,456 MW in SeptemberERCOT monthly operational overview, September (Oct 16)
ERCOTBatch One, for requests outside Batch Zero, targeted to launch in June 2027Data Center Frontier, Aug 31
ERCOTThe 2025 forecast method counted new data center requests at 49.8%; average in-service slip about 220 daysERCOT Board, Item 8.1, Apr 7, 2025
ERCOTPreliminary 2026 forecast: 39.7 GW of new data center load in 2027 rising to 211.6 GW in 2031, from utility-submitted requests; ERCOT calls it preliminaryERCOT Board, CEO update, Apr 15
ERCOTPreliminary all-time peak demand of about 91.1 GW on Jul 22, 2026Forbes, Oct 13
PUCT16 TAC §25.194 adopted Sep 18: $50,000 per MW of security, a $100,000 initial fee plus tiered study charges, for loads of 75 MW or moreWhite & Case, Sep 25
Outside viewBNEF: the pause could delay 49.8 GW of data center load; about 8.25 GW of additions in ERCOT through 2030POWER, Aug 6
Outside viewCenterPoint expects 3, 8, 11 and 12 GW of Batch Zero load energized in 2027–30; about 2 GW of studied load withdrawnS&P Global, Oct 27
Outside view92 GW of advanced-planning data center load in ERCOT: 11 operating or expanding, 12 under construction, 15 committedModo Energy, Oct 21
Curtailment525.5 MW of uncompensated emergency curtailment on two Crusoe data centers behind one wind farm (Docket 59220); 933 MW of off-grid gas turbines under construction at the Armstrong County site (no source given)Global Data Center Hub, Aug 26
NexusAnthropic campus, 1.6 GW on-site gas plant; about $15B of financing in talks, with Google guaranteeing Anthropic’s lease and power payments (WSJ’s account)Global Data Center Hub (WSJ), Aug 3
NexusGoogle agreed to guarantee the senior debt; $1.3B mezzanine loan closed; final investment decision reachedThe Next Web (Bloomberg), Aug 20
Nexus, FrontierMajor-source air permit notices mailed Sep 22 for Nexus Hubbard and VoltaGrid’s Frontier plantPublic Citizen permit summary
NexusState building filings: HB1 to Oct 2027, HB2 to Jan 2028DCD
Frontier1.4 GW of critical IT in 10 buildings; first building 2H 2026Vantage Data Centers
FrontierAbout 700 MW from 210 gas engines, approved by TCEQ per filingsConstruction Owners (Business Insider), Oct 24, 2025
FrontierProjected building dates Aug 2027 to Nov 2028 (estimate)Epoch AI
Abilene900 MW campus for Microsoft with its own power plant; first building mid-2027; the 1.2 GW Stargate campus complete by end-2026Crusoe, Mar 27
AbilenePSD application by Crusoe for added generation at the Longhorn data center, under technical review; the link to Microsoft’s expansion is oursTCEQ notice 182126
Kilby20-year power agreement with Microsoft; about 2.67 GW of gas; FID by end-2026; first power 2028Chevron, Jun 22
KilbyIslanded campus, about 2 GW of data centers over 5–7 yearsGlobal Data Center Hub, Jun 29
KilbyOnly a minor-source permit-by-rule application found at TCEQPublic Citizen permit summary
CameronFluidstack, up to 1.5 GW with on-site generation; phase 1 mid-2028The Energy Mag, Sep 22
MilamOpenAI 1.2 GW lease; SB Energy builds new generationOpenAI, Jan 9
ChildressCrusoe and Lancium 1 GW campus; construction Q3 2026Crusoe, Jul 15
ChildressMeta contracts about 1.6 GW from Crusoe across Childress and Missouri (reported)DCD (Bloomberg)
Google, AmazonCampus power capacities (Armstrong ~1,065 MW, Wilbarger ~850 MW, Meitner ~840 MW); secondaryCleanview
Comanche Peak1.2 GW nuclear PPA for Amazon; energize 2027; Vistra says the pause doesn’t affect itUtility Dive, Aug 10
GW Ranch7.65 GW gas air permit issued; phase 1 of 1 GW with first power H1 2027Pacifico Energy (BusinessWire), Jan 26
GW RanchAmazon acquired the site in August (secondary)Let’s Data Science, Aug 8
El PasoEl Paso Electric’s 366 MW McCloud plant for Meta; judges recommend approval only if Meta bears the costInside Climate News, Sep 24
HeliosBase and studied classifications for Helios I–II and 2.6 GW of other sitesGalaxy, Sep 8
HeliosPhase II deliveries from Q2 2027; Helios II without a tenant; TCEQ freeze not expected to affect timelinesBigGo Finance (Galaxy Q3 call), Oct 27
CipherColchis 1 GW base load; 1.6 GW studied; laterals for up to 2.5 GW of on-site generationCipher Digital, Nov 2
CipherBarber Lake lease extended to 20 years, about $9.1BCipher Digital, Nov 2
IREN2 GW Sweetwater hub included as Batch Zero base loadIREN, Sep 8
IRENHorizon 1 delivered to Microsoft at ChildressIREN FY26 results, Aug 27
Riot, Hut 8Rockdale 191 MW IT for an AI lab; Beacon Point 704 MW IT leased (secondary ledger citing company releases)Regards of Wall Street
FermiTensorWave lease not effective after the Oct 31 closing date passedFermi (via StockTitan), Nov 3
FermiAbout 2 GW targeted by end-2027; a further ~5 GW air permit filed Mar 27Converge Digest (Fermi 10-K), Mar 30
HorizonCoreWeave’s deal with Poolside fell apartBaxtel (Financial Times), Apr 4
SailfishHood County rejected the Comanche Circle settlement and permit appealTexas Public Radio, Oct 13
San AntonioNotice of intent to sue Vantage and VoltaGrid over off-grid permitsBaxtel, Jul 24

Method

What the paths count. New data center load switched on in Texas after September 2026, at quarter-ends through 2030, in five parts. ERCOT’s 17 cleared loads enter at 6.9 GW, the size of its November cohort of 17 loads, which we take to be the same ones, at their full requested peak; ERCOT gives that peak over five years, and we ramp it evenly. Batch Zero’s base load, 66.4 GW, is cut to the 49.8% realization rate of ERCOT’s 2025 forecast method, less the cleared loads, which we assume are part of it (26.2 GW), and ramps evenly from July 2027 to December 2032. Named self-powered campuses with permits pending (Nexus, Frontier’s second half, Abilene for Microsoft, Pecos) and with permits issued (Frontier’s first half, GW Ranch’s first phase, Meitner, the San Antonio pair) follow their announced or estimated dates, and the campuses outside ERCOT (El Paso, Abernathy) theirs. Batch Zero’s studied load (allocations from 2028, pending a study that hasn’t restarted) and the excluded 302 GW (waiting for Batch One) aren’t in the paths; we judge neither likely to arrive in volume before 2029. Fluidstack’s Cameron County site isn’t modeled separately: its grid request is in ERCOT’s queue, probably mostly in studied load.

Before the freeze. The cleared loads start in December 2026, base load in July 2027, and every named campus on its own date. Abbott’s path moves the cleared loads to Q2 2027, when ERCOT slates its November cohort, base load by three months, and permits pending on September 21 by the 4.3 months to the end of January.

Hinojosa’s path. A moratorium on new data centers runs from inauguration to the date picked (June 20, September 1 or December 31, 2027). It reaches 75% of base load, all pending own-gas permits and a quarter of the issued-permit and out-of-ERCOT campuses; it reaches the cleared loads only if the commission hasn’t approved them before January 19, which we put at even odds, and then half of them. Because the agencies are run by Abbott appointees and an order can be challenged, only part of the moratorium holds: 60% with Hinojosa alone, 80% with the lieutenant governor too and 90% with the Texas House as well. Each part’s schedule moves later by the share that holds times the months between the end of January and the moratorium’s end. Cancellations take a share of what each part adds after inauguration, across the three outcomes: 3–8% of base load, 10–20% of pending own-gas campuses, 3–8% of issued-permit campuses and 2–5% of those outside ERCOT, for local vetoes, a tax repeal without grandfathering and developers moving elsewhere. All of these are judgments, not data. The pace matters most: at a 25% realization of base load the base-case gap at the end of 2028 is 2.0 GW, at 100% it is 4.6 GW. Our Abbott path, about 30 GW of new data center load by 2030, is well above BNEF’s outlook of about 8 GW of additions in ERCOT through 2030; CenterPoint alone expects 12 GW of Batch Zero load of all kinds switched on in its territory by 2030.

Exposure ratings are ours: high where a tenant-backed campus waits on a TCEQ air permit for power due in 2027–28; medium where it waits on an ERCOT switch-on, a commission vote or a contested permit; low where it is switched on or holds its approvals; company risk where its own financing or tenant, not the state, sets its timing. Results are unofficial counts and race calls as reported, with the time of each.