W.033TeraWulf’s lease revenue nearly doubled in a quarter, to $63M. It spent $852M building more in the same three months

TeraWulf’s high-performance computing lease revenue rose 97% from the second quarter to $63.0M, 83% of its sales; bitcoin mining was 17%. Capital spending in the quarter was about $852M, 11 times revenue. 102 MW of critical IT load was earning rent at Lake Mariner at September 30, about an eighth of the roughly 839 MW it has under lease. Management told analysts it expects about $700M of annualized leasing revenue on exiting the first quarter of 2027.

HPC lease revenue, Q3
$63.0M
+97% on Q2; 83% of revenue
Capital spending, Q3
$852M
11.2× the quarter’s revenue
Leased capacity earning rent
102 MW
of about 839 MW under lease
Debt, carrying value
$5.2B
cash incl. restricted $2.4B

The miner is now a landlord

Leases are more than four-fifths of revenue. TeraWulf’s revenue was $76.2 million in the third quarter. Lease revenue from its high-performance computing tenants was $63.0M, up from $31.9M in the second quarter and $7.2M a year earlier; Fluidstack’s CB-3 building at Lake Mariner, New York, was fully delivered in early July, lifting revenue-generating capacity to 102 MW from 81 MW at June 30. Bitcoin mining brought in $13.2M, 69% less than a year earlier. Adjusted EBITDA was a loss of $12.8 million, against a profit of $18.1 million a year earlier. Net income attributable to the company was $709.9 million because of a $728.4 million gain on the fair value of warrant and derivative liabilities; diluted earnings per share were a loss of 3 cents.

The build is running at about $850 million a quarter. Purchases of and deposits on property, plant and equipment were $2,231 million in the first nine months, against $445 million a year earlier; by our subtraction about $852 million of it fell in the third quarter, when operations used about $25 million of cash. Cash, including restricted cash, fell to $2.36B from $3.03B at June 30. Debt at carrying value was about $5.23B: $3,113 million of long-term debt, mainly the 7.75% notes that funded Lake Mariner, and $2,119 million of convertible notes. The company sold $1,200 million of stock, net, in the nine months. On the call, according to an AI-generated transcript, chief financial officer Patrick Fleury put the remaining spend on the Lake Mariner build at about $1 billion, about two-thirds of it committed, and said the contracted build and its Kentucky equity can be funded without new stock.

Lease revenue is 83% of sales

TeraWulf revenue by quarter, $ millions: HPC lease revenue (the latest quarter highlighted) and digital asset (bitcoin mining) revenue, with lease revenue’s share of the total over each bar. Q4 2025 segment figures are rounded to $0.1M in the full-year release.

HPC leasesBitcoin mining
0$30M$60M$90MQ3 2025: HPC lease revenue $7.2MQ3 2025: digital asset revenue $43.4M14% HPCQ325Q4 2025: HPC lease revenue $9.7MQ4 2025: digital asset revenue $26.1M27% HPCQ4Q1 2026: HPC lease revenue $21.0MQ1 2026: digital asset revenue $13.0M62% HPCQ126Q2 2026: HPC lease revenue $31.9MQ2 2026: digital asset revenue $12.8M71% HPCQ2Q3 2026: HPC lease revenue $63.0MQ3 2026: digital asset revenue $13.2M83% HPCQ3
0$30M$60M$90MQ3 2025: HPC lease revenue $7.2MQ3 2025: digital asset revenue $43.4M14% HPCQ325Q4 2025: HPC lease revenue $9.7MQ4 2025: digital asset revenue $26.1M27% HPCQ4Q1 2026: HPC lease revenue $21.0MQ1 2026: digital asset revenue $13.0M62% HPCQ126Q2 2026: HPC lease revenue $31.9MQ2 2026: digital asset revenue $12.8M71% HPCQ2Q3 2026: HPC lease revenue $63.0MQ3 2026: digital asset revenue $13.2M83% HPCQ3
Data
QuarterHPC leaseDigital assetTotalHPC share
Q3 20257.243.450.614.2%
Q4 20259.726.135.827.1%
Q1 202621.013.034.061.8%
Q2 202631.912.844.871.3%
Q3 202663.013.276.282.6%

Each quarter of 2026 cost more than ten times its revenue

TeraWulf purchases of and deposits on property, plant and equipment by quarter of 2026, $ millions (our subtraction of cumulative cash flow figures), against total revenue in the same quarter. Excludes $234.7M of asset acquisitions in the nine months.

Capital spendingRevenue
0$250M$500M$750M$1000MQ1 2026Q1 2026: purchases of and deposits on PP&E $523.0Mcapex $523MQ1 2026: revenue $34.0Mrevenue $34MQ2 2026Q2 2026: purchases of and deposits on PP&E $855.5Mcapex $856MQ2 2026: revenue $44.8Mrevenue $45MQ3 2026Q3 2026: purchases of and deposits on PP&E $852.3Mcapex $852MQ3 2026: revenue $76.2Mrevenue $76M
0$250M$500M$750M$1000MQ1 2026Q1 2026: purchases of and deposits on PP&E $523.0M$523MQ1 2026: revenue $34.0M$34MQ2 2026Q2 2026: purchases of and deposits on PP&E $855.5M$856MQ2 2026: revenue $44.8M$45MQ3 2026Q3 2026: purchases of and deposits on PP&E $852.3M$852MQ3 2026: revenue $76.2M$76M

From 102 MW to about 839

Most of the leased capacity has yet to be delivered. At September 30, 102 MW was operating and earning rent at Lake Mariner, which by the company’s figures covers Core42’s 60 MW and Fluidstack’s CB-3; 336 MW was under construction in CB-4 and CB-5. CB-4, up to 168 MW, starts phased rent in the fourth quarter, and CB-5 is to be delivered in phases from early 2027. In Kentucky, the roughly 401 MW Justified campus leased to Anthropic for about $19 billion over 20 years is due to be ready in phases from late 2027 through the second quarter of 2028; in August TeraWulf had said full delivery in early 2028. Together that is about 839 MW, of which 12% was earning rent.

The run-rate target is close to three times the third quarter. On the call, according to two transcripts, chief executive Paul Prager said TeraWulf expects about $700 million of annualized leasing revenue as it exits the first quarter of 2027, with about half of contracted capacity operating; four times the third quarter’s lease revenue is about $252 million. Prager said TeraWulf would not sign a lease that forces it to issue equity at a valuation it does not believe in, and that it is in talks with prospective tenants he did not name. TeraWulf also doubled the power contracted for its Muskie site in Kentucky to 1,000 MW, subject to approval by the state’s Public Service Commission, with the second 500 MW expected in 2029. Its shares rose 8.73% to $10.96 before the open, Seeking Alpha reported.

About an eighth of the leased capacity is earning rent

TeraWulf critical IT capacity under lease, MW, by building, with tenant and expected timing under each name: operating at September 30 (solid) and under construction or not yet started (outlined). CB-4 is “up to” 168 MW; CB-5 and Justified are approximate. Fluidstack’s three Lake Mariner leases total 378 MW in the 2025 10-K.

0100200300400Lake Mariner, operatingCore42 and Fluidstack CB-3Lake Mariner, operating: about 102 MW, earning rent at Sep 30102 MW, earning rentLake Mariner CB-4Fluidstack; Q4 2026Lake Mariner CB-4: up to 168 MW, phased rent from Q4 2026up to 168 MWLake Mariner CB-5Fluidstack; early 2027Lake Mariner CB-5: about 168 MW, phased from early 2027~168 MWJustified, KentuckyAnthropic; late 2027–Q2 2028Justified, Kentucky: about 401 MW, late 2027 to Q2 2028~401 MW
0100200300400OperatingCore42, CB-3Lake Mariner, operating: about 102 MW, earning rent at Sep 30102 MWCB-4Q4 2026Lake Mariner CB-4: up to 168 MW, phased rent from Q4 2026168 MWCB-5early 2027Lake Mariner CB-5: about 168 MW, phased from early 2027168 MWJustifiedfrom late 2027Justified, Kentucky: about 401 MW, late 2027 to Q2 2028401 MW

The target is 2.8 times the current run-rate

TeraWulf leasing revenue, annualized, $ millions: third-quarter HPC lease revenue times four (our calculation); management’s target on exiting the first quarter of 2027, from the call; and the Anthropic lease’s $19B divided evenly over its 20-year initial term (our calculation; actual rent will ramp and may escalate).

0$250M$500M$750M$1000MQ3 2026 lease revenue × 4our calculationQ3 2026 lease revenue × 4: about $252M$252MTarget on exiting Q1 2027management, on the callTarget on exiting Q1 2027: about $700M~$700MAnthropic lease, a year$19B over 20 years, averagedAnthropic lease, a year: about $950M~$950M
0$250M$500M$750M$1000MQ3 × 4our calculationQ3 2026 lease revenue × 4: about $252M$252MQ1 2027 exittarget (call)Target on exiting Q1 2027: about $700M~$700MAnthropic lease$19B ÷ 20 yearsAnthropic lease, a year: about $950M~$950M

What this changes on 06.ai

  • Neocloud capex funding pack: TeraWulf is now a quarterly series for a converted miner’s ratio of build spending to lease revenue (about 11× in the third quarter) and for leased megawatts earning rent against those signed (12%).
  • Watch: the ~$700M exit run-rate for the first quarter of 2027 is a dated, checkable target; the Q1 2027 results, due around May, will show it.

Sources and method

ItemFigureSource
Q3 2026Revenue $76.2M: HPC lease $62.986M, digital asset $13.244M (Q3 2025 $7.203M and $43.375M); net income attributable $709.9M, including a $728.4M gain on warrant and derivative liabilities; adjusted EBITDA −$12.8M; 102 MW revenue-generating critical IT at Lake Mariner; 336 MW under construction at CB-4 and CB-5; Justified about 401 MW for Anthropic, about $19B, phased ready-for-service late 2027 to Q2 2028; Muskie contracted power 500 → 1,000 MW subject to PSC approval; nine-month PP&E purchases and deposits $2230.8M ($445.2M); operating cash flow −$178.9M; debt and cash balances; $1199.8M of stock issued, netTeraWulf Q3 release, Nov 6
Q2 2026HPC $31.932M, digital asset $12.835M; six-month PP&E purchases and deposits $1378.5M; operating cash flow −$154.3M; Anthropic lease up to about $33B with extensionsTeraWulf Q2 release (8-K), Aug 5
Q1 2026HPC $21.022M, digital asset $12.99M; PP&E purchases and deposits $523M; Core42’s 60 MW operationalTeraWulf Q1 release (8-K), May 8
Q4 2025HPC $9.7M, digital asset $26.1MTeraWulf Q4 2025 release, Feb 26
LeasesCore42 60 MW at Lake Mariner; Fluidstack leases of 378 MW at CB-3, CB-4 and CB-5TeraWulf 2025 10-K
CallAbout $700M of annualized leasing revenue on exiting Q1 2027; CB-4 up to 168 MW; about $1B left to spend at Lake Mariner; no lease that forces an equity raiseQ3 call transcript (AI-generated), gloom.sh
CallSecond summary of the call: run-rate target, revolver to about $550M with accordionQ3 call summary, stocknow.ai
SharesUp 8.73% to $10.96 before the open, 8:11 ETSeeking Alpha, Nov 6

Revenue: HPC 62.986 ÷ 31.932 − 1 = 97.3%; share 62.986 ÷ 76.230 = 82.6%; mining 13.244 ÷ 43.375 − 1 = -69.5%. Q4 2025 total is the sum of its two segments.

Capital spending: Q2 = 1378.5 − 523 = 855.5; Q3 = 2230.8 − 1378.5 = 852.3; ÷ revenue 76.2 = 11.2×. Q3 operating cash flow = -178.9 − (-154.3) = -24.6. Debt: 3032.1 + 81.3 + 1627.3 + 491.5 = 5232.2, carrying values. Capacity: 102 operating + 168 + 168 under construction (the release’s 336 MW) + 401 = 839 MW; 102 + 336 = 438 matches Core42’s 60 MW plus Fluidstack’s 378 MW. Share earning rent 102 ÷ 839 = 12.2%. Run-rates: 62.986 × 4 = 251.9; 19000 ÷ 20 = 950; 700 ÷ 251.9 = 2.78. Call remarks come from AI-generated transcripts and are attributed as such.