W.009Drax’s £20B data centre is seven times Drax, and mostly conditional

Drax has signed an agreement to develop a partnership with Brookfield and its AI infrastructure company Radiant for a data centre at Drax Power Station in North Yorkshire. Brookfield estimates the investment, chips included, could exceed £20B, about 7 times Drax’s market value. Only the first 100MW, an initial £2.5B, has a target operating date, the first quarter of 2028, subject to planning, a tenant and final investment decisions.

Total potential investment, Brookfield’s estimate
>£20B
including chips; about 7.4× Drax’s £2.7B market value
Phase 1, from Q1 2028
100MW
“up to”; an initial £2.5B, about £25M per MW
Target, after 2031
>1GW
Phase 2’s 500MW needs Government approval under Drax’s subsidy contract
Drax shares, Nov 3
+8.6%
to 878.5p intraday, top FTSE 250 riser (AJ Bell)

A dated first 100MW, then an ambition

Data centre capacity, cumulative MW, by phase as Drax’s release describes them. Solid is Phase 1, dated to Q1 2028 and still conditional; outlined is capacity described as an ambition or a target. Every figure is “up to” or “more than.”

Phase 1, datedAmbition or target
0400MW800MW1,200MWPhase 12026–28Phase 1: up to 100MW; commercial operation from Q1 2028; grid-powered through existing station infrastructureup to 100MWPhase 22028–31Before Phase 2: up to 100MWPhase 2: an ambition for up to 500MW more, behind the meter from Drax’s own generation; needs UK Government and LCCC agreement under Drax’s contract for differenceup to 600MWPhase 3after 2031Before Phase 3: up to 600MWPhase 3: further capacity, to a target of more than 1GW in all>1GW target
0400MW800MW1,200MWPhase 12026–28Phase 1: up to 100MW; commercial operation from Q1 2028; grid-powered through existing station infrastructure100MWPhase 22028–31Before Phase 2: up to 100MWPhase 2: an ambition for up to 500MW more, behind the meter from Drax’s own generation; needs UK Government and LCCC agreement under Drax’s contract for difference600MWPhase 3after 2031Before Phase 3: up to 600MWPhase 3: further capacity, to a target of more than 1GW in all>1GW
Data
PhaseWhenAddsCumulativeAs described
Phase 12026–28up to 100MWup to 100MWup to 100MW; commercial operation from Q1 2028; grid-powered through existing station infrastructure
Phase 22028–31up to 500MWup to 600MWan ambition for up to 500MW more, behind the meter from Drax’s own generation; needs UK Government and LCCC agreement under Drax’s contract for difference
Phase 3after 2031further capacity>1GWfurther capacity, to a target of more than 1GW in all

What was signed

The release describes an agreement to develop a partnership, not a final contract. Radiant would lead design, customers and commercial terms; Drax would provide “powered land” and lead planning and power integration; capital and operations would come through Brookfield’s AI infrastructure venture with Qatar’s Qai. Phase 1 depends on planning, regulatory and network approvals, “an acceptable tenant”, commercial agreements and a final investment decision by each party. Public consultation is expected to start this month. The release discloses no ownership split and no payments to Drax.

The £20B is Brookfield’s estimate of what could be invested, and it includes chips. Most of a GPU data centre’s cost is the servers, so the figure is not comparable with announcements that cover only buildings and power. Phase 1’s initial £2.5B for up to 100MW is about £25M per MW; the release doesn’t say whether that includes chips. Citi wrote that the announcement reads more like a memorandum of understanding than a firm contract, according to Reuters; JPMorgan said Brookfield’s involvement adds credibility.

What changed since December is a partner and a price, and the date slipped. In December 2025 Drax set out a first phase of about 100MW “as soon as 2027” with options above 1GW, but no partner and no capital figure; the shares rose to 770p. Phase 1 is now dated to the first quarter of 2028.

The headline figure is seven times the company

£B. Drax’s market value as reported on the morning of November 3, after the shares rose; Phase 1’s initial investment; and Brookfield’s estimate of total potential investment, including chips, which “could exceed” £20B. None of it is committed until each party takes a final investment decision.

0£5B£10B£15B£20BDrax market valueNov 3, after the riseDrax market value: about £2.7B (AskTraders)~£2.7BPhase 1“initial”, up to 100MWPhase 1: an initial £2.5B£2.5BTotal potentialBrookfield estimate, with chipsBrookfield estimates total potential investment, including chips, could exceed £20Bmore than £20B
0£5B£10B£15B£20BDrax valueDrax market value: about £2.7B (AskTraders)~£2.7BPhase 1Phase 1: an initial £2.5B£2.5BTotalBrookfield estimates total potential investment, including chips, could exceed £20B>£20B

The station could feed it; the subsidy contract decides how much

MW. Drax’s four biomass units; their average output if run at the 27% load factor cap in the 2027–31 bridging contract for difference; and the data centre (DC) as phased. Phase 2’s up to 500MW would run behind the meter from Drax’s own generation, which needs Government and Low Carbon Contracts Company agreement under that contract.

01,000MW2,000MW3,000MWBiomass generation4 units × 645MWDrax biomass capacity: 4 × 645MW = 2,580MW2,580MWAt the 27% load factor capaverage, 2027–31 contract2,580MW × 27% = about 697MW on average~697MWData centre by 2031Phases 1 and 2, “up to”Phase 1: up to 100MWPhase 2: up to 500MW more, an ambitionup to 600MWData centre targetafter 2031Target: more than 1GW>1GW
01,000MW2,000MW3,000MWGenerationDrax biomass capacity: 4 × 645MW = 2,580MW2,580MWAt 27% cap2,580MW × 27% = about 697MW on average~697MWDC by 2031Phase 1: up to 100MWPhase 2: up to 500MW more, an ambition≤600MWDC targetTarget: more than 1GW>1GW

The site also has about 4GW of grid access, according to Data Centre Review, which is why Phase 1 can run from the grid through the station’s existing connection. The 27% cap limits the subsidised output; it is shown as a scale, not as a forecast of what Drax will generate.

Against the rest of the UK pipeline

A gigawatt would be a large share of what Britain runs today. UK data centres use around 2GW of electricity, according to a government estimate reported by The Register, and the government’s July 2025 Compute Roadmap targets 6GW of AI-capable data centre capacity by 2030. The queue for grid connections is far larger: Ofgem said in July that data centres account for at least 80GW of contracted demand, as it set out measures against speculative projects. A site with a connection and its own generation is what the queue lacks, which is Drax’s case for the project.

Other announced projects are priced on different bases. QTS (Blackstone), Cambois: “up to £10bn”, 720MW of IT load; Brookfield, Cambrai (France): about €15bn of a €20bn French plan, “up to one gigawatt”; Brookfield, Strängnäs (Sweden): up to SEK 95bn (about $9.9bn), 750MW over 10–15 years. None says clearly whether chips are included, so a cost per megawatt across them would not compare like with like.

The power source is contested. Drax burns wood pellets, mostly imported from North America. Environmental groups quoted by the BBC criticised a data centre run on biomass; in 2024 Drax paid £25M into a redress fund after Ofgem found it had reported inaccurate data on where its wood came from, while finding no evidence the biomass was unsustainable.

What this changes on 06.ai

  • Series lead: UK and European AI data centre announcements with MW, phase dates, the stated investment and whether it includes chips. Drax’s phase 1 (up to 100MW, £2.5B, Q1 2028) is a dated, checkable entry; the £20B is not.
  • Pack lead (015, who funds the neoclouds): Radiant, Brookfield’s GPU cloud, would lead commercialisation and customers here. If Phase 1 reaches a final investment decision, its tenant and financing are a data point for the neocloud funding pack.

Sources and method

ItemFigureSource
The agreementSigned an agreement to develop a strategic partnership; Radiant leads design and customers, Drax provides powered land; Phase 1 up to 100MW from Q1 2028 with an initial £2.5bn; Phase 2 an ambition for up to 500MW more in 2028–31, behind the meter, needing Government and LCCC agreement; target above 1GW; total potential investment, including chips, could exceed £20bn (Brookfield estimate); conditions: planning, network approvals, an acceptable tenant, final investment decisionsDrax, Nov 3
The agreementRNS text (mirror)Investegate
SharesUp 8.6% to 878.5p, top FTSE 250 riserAJ Bell, Nov 3
SharesUp 8.78% to 880p at 08:15; market value about £2.7bnAskTraders, Nov 3
AnalystsCiti: reads more like a memorandum of understanding than a firm contract; JPMorgan: Brookfield adds credibilityReuters via Yahoo Finance, Nov 3
SiteAbout 4GW of grid access, 2.6GW of dispatchable generation, more than 1,000 acresData Centre Review, Nov 3
Bridging contractFour 645MW biomass units; contract for difference April 2027 to March 2031, strike £113/MWh (2012 prices), load factor capped at 27%Enerdata, Feb 11, 2025
Earlier planDec 2025: about 100MW first phase as soon as 2027, options above 1GW, no partner; shares to 770pAJ Bell, Dec 11, 2025
RadiantBrookfield’s AI cloud unit, merged with London-based Ori; valued at $1.3bnReuters via Global Banking & Finance, Feb 27
PeersQTS Cambois: up to £10bn, 720MWDCD
PeersBrookfield France: €20bn by 2030, about €15bn for an up-to-1GW campus at CambraiMaginative, Feb 2025
PeersBrookfield Sweden: up to SEK 95bn, 750MW at Strängnäs over 10–15 yearsDCD, Jun 2025
CriticismEnvironmental groups’ criticism of a biomass-powered data centre; local MP and science minister supportiveBBC via Yahoo, Nov 3
Ofgem, 2024Drax paid £25m to a redress fund over inaccurate biomass sourcing data; no evidence the biomass was unsustainableITV, Aug 29, 2024
UK context6GW of AI-capable data centre capacity needed by 2030 (Compute Roadmap, July 2025)DCD
FuelDrax’s wood pellets come largely from the US South and CanadaLouisiana Illuminator, Feb 9
UK contextData centres are at least 80GW of contracted demand in the connection queueOfgem, Jul 29
UK contextUK data centres use around 2GW of electricity, per a government estimate; the £20bn is “more ambition than actual money”The Register, Nov 3

Phases are as Drax’s release describes them; cumulative capacity adds Phase 1’s up to 100MW and Phase 2’s up to 500MW to give up to 600MW by 2031, and Phase 3 is drawn to the 1GW target, which the release says would be exceeded. The multiple is £20B ÷ £2.7B = 7.4, using AskTraders’ market value on the morning of November 3. Phase 1 per MW is £2.5B ÷ 100MW = £25M. The share move is AJ Bell’s intraday reading (878.5p, up 8.6%); a closing price was not found.

Station capacity is 4 × 645MW = 2,580MW. Average output at the cap is 2,580MW × 0.27 = 697MW; the cap is the load factor limit Enerdata reported for the bridging contract (April 2027 to March 2031, strike £113/MWh in 2012 prices). Drax’s release puts the contracted volume at about 6TWh a year, about 30% of baseload output; 697MW for a year is about 6.1TWh.