W.045CoreWeave asked Texas’s governor-elect to let permitted projects finish. About 64% of the power it had contracted was not switched on in mid-2026, and its largest disclosed Texas lease is a quarter delivered
CoreWeave’s chief executive wrote to Texas Governor-elect Gina Hinojosa on November 7, two days after she said the state should stop what it is doing with data centers until residents have legal protections. The company had about 4.2 GW of contracted power on August 11 and more than 1.5 GW active at the end of June, leaving up to about 2.7 GW to switch on. At Galaxy’s Helios campus in Dickens County, one of six Texas locations the letter names, 133 MW of the 526 MW of critical IT load leased to CoreWeave has been delivered; the next 260 MW is due to start arriving in the second quarter of 2027.
The letter
CoreWeave offered to work with Texas’s incoming governor on the projects it has under way. In a two-page letter dated November 7, reported by Bloomberg, chief executive Michael Intrator offered to work with Gina Hinojosa’s transition team on the completion of permitted projects and on standards for future development, Investing.com reported. The letter restates her position that data center growth must work for Texans and says CoreWeave strongly supports her principles. According to FourWeekMBA’s account of the pages, which were posted on X, the letter welcomes her clarification that currently permitted projects can finish, says CoreWeave pays for the substations and transmission upgrades its new grid connections need so that the costs are not passed on to households, and says its new capacity uses closed-loop liquid cooling. It lists active facilities in Austin, Denton, Dickens County, Plano, Richardson and Round Rock. Its only power figures are company-wide, the ones below; it gives no Texas megawatts and no dollar figures. No reply from Hinojosa’s team had been reported.
Hinojosa, a Democrat, won on November 3 and takes office in January. On November 5 she said Texas needs to stop what it is doing with data centers until there are protections for residents; reports of her later remarks say permitted projects could finish and a pause would apply to new permits, but we found no transcript. Texas had already slowed the pipeline under her Republican predecessor: on August 3, Gov. Greg Abbott ordered the state’s utility regulator and grid operator to audit data centers in the grid connection queue, and on September 21 he told the state environmental regulator to halt data center permits until that audit is done. CoreWeave reports its third quarter on November 10.
About 2.7 GW of CoreWeave’s contracted power is still to come
CoreWeave’s active power (solid) and contracted power (outlined to the total), gigawatts, as the company reported them. June 30, 2025: about 470 MW active, about 2.2 GW contracted. June 30, 2026: active power reached 1.5 GW (the infographic says 1.5GW+), contracted about 3.7 GW. August 11, 2026: contracted about 4.2 GW; no active figure was given for that date. CoreWeave does not say whether these are critical IT or gross megawatts, and gives no split by state.
What is built and what is not
Most of what CoreWeave had contracted was not running at mid-year. It reported active power of 1.5 GW or more at June 30, across 51 data centers, about 3.2 times the roughly 470 MW a year earlier. Contracted power reached about 4.2 GW by August 11, 1.9 times the 2.2 GW of June 30, 2025. The difference, up to about 2.7 GW or 64% of the contracted total, is capacity CoreWeave has agreed to take but had not switched on; the two figures are six weeks apart, so this is an approximation. CoreWeave does not say how much of either is in Texas.
The largest Texas site with public megawatts is mostly unbuilt. Galaxy leases CoreWeave 526 MW of critical IT load, 800 MW of gross power, at its Helios campus in Dickens County, over 15-year base terms. Galaxy delivered all 133 MW of the first phase by the end of June. The second phase, 260 MW, is fully financed and under construction, with data hall deliveries scheduled to begin in the second quarter of 2027; the rest, 133 MW by our arithmetic, has no published date. Galaxy expects more than $1.2B a year in revenue, on average, across the full 526 MW. On October 27 it reported 830 MW of approved capacity at Helios II not yet under lease. The Texas pack lists Helios among the grid-tied campuses that already hold ERCOT approval.
One other location has a public figure. Core Scientific said in February 2025 that an expansion for CoreWeave would bring its Denton site to approximately 260 MW of critical IT, adding about $1.2 billion of contracted revenue, part of about 590 MW it has committed to CoreWeave across six sites. CoreWeave announced a $1.6 billion, 450,000-square-foot facility in Plano in July 2023, without a megawatt figure. We found no capacity figures for Austin, Richardson or Round Rock.
Three-quarters of Helios is still to be delivered
Critical IT load Galaxy leases to CoreWeave at Helios, Dickens County, Texas, megawatts, by phase. Solid: delivered (Phase I, by the end of June 2026). Outlined: not yet delivered. Phase II’s data hall deliveries are scheduled to begin in the second quarter of 2027. Phase III is our arithmetic, the 526 MW total less the first two phases; Galaxy gives no date for it.
The backlog and the balance sheet
CoreWeave’s contracted revenue stretches about six and a half years out. Its revenue backlog was about $104B at June 30, 3.5 times the $30.1B of a year earlier, and it said more than $25B of net new commitments came in early in the third quarter. Its quarterly filing expects 41% of its $103.7B of remaining performance obligations to be recognized within 24 months and 39% in the following two years. Second-quarter revenue was $2.58B, up 112% from a year earlier, a pace of about $10.3B a year. In August it raised its 2026 capital spending guidance to $35–39B.
Its shares and bonds fell after the election. CoreWeave’s shares fell 9.83% to $43.66 on November 5 and were down 47.54% over a month, 24/7 Wall St. reported. Its 9.625% notes due 2032 yielded above 16% on November 6, and the price of five-year default protection was above 1,289 basis points on November 5 before easing to about 1,155 the next day. W.029 covers its debt in detail.
Two-fifths of the backlog is due within two years
CoreWeave’s remaining performance obligations at June 30, 2026 ($103.7B), split by when the company expected to recognize them as revenue, per its 10-Q: 41% within 24 months, 39% in months 25–48 and the rest in months 49–78. Dollar amounts are our arithmetic from those shares. The figure excludes the more than $25B of commitments added in early Q3.
The figures behind the charts
| Item | As of | Value |
|---|---|---|
| Contracted power | June 30, 2025 | ~2.2 GW |
| Contracted power | June 30, 2026 | ~3.7 GW |
| Contracted power | August 11, 2026 | ~4.2 GW |
| Active power | June 30, 2025 | 0.47 GW |
| Active power | June 30, 2026 | 1.5 GW |
| Helios, Phase I (delivered) | June 30, 2026 | 133 MW |
| Helios, Phase II | from Q2 2027 | 260 MW |
| Helios, Phase III (derived) | no date | 133 MW |
| RPO, within 24 months | June 30, 2026 | $42.5B |
| RPO, months 25–48 | June 30, 2026 | $40.4B |
| RPO, months 49–78 | June 30, 2026 | $20.7B |
What this changes on 06.ai
- Texas pack: CoreWeave has now named six Texas locations with active facilities and said publicly that it pays for its own substations and transmission upgrades. Of the six, only Helios (526 MW leased) and Denton (about 260 MW, per Core Scientific in 2025) have public megawatts. Helios’s 393 MW still to be delivered (Phases II and III) is likely the largest block of CoreWeave capacity in Texas we can size that a pause on unbuilt projects could reach; whether Phase III is permitted is not public.
- Neocloud capex pack: on November 10, update CoreWeave’s active and contracted power, backlog and 2026 capital spending guidance; the gap between contracted and active power (about 2.7 GW in August) is the series to watch.
- Watch Galaxy’s next quarterly report for whether Helios Phase II is still on schedule for the second quarter of 2027.
Sources and method
| Item | Figure | Source |
|---|---|---|
| Letter | Two-page letter from CEO Michael Intrator to Governor-elect Gina Hinojosa, Nov 7; offers to work with her transition team on completing permitted projects and on standards for future development | Bloomberg; Investing.com, Nov 7 |
| Letter | Names active sites in Austin, Denton, Dickens County, Plano, Richardson and Round Rock; says CoreWeave funds substations and transmission upgrades for new connections; closed-loop liquid cooling for new capacity; welcomes her clarification that permitted projects can finish; restates her position that data center growth must work for Texans; company-wide figures only (51 data centers, more than 1.5 GW active, about 4.2 GW contracted); no Texas megawatts, no dollar figures | FourWeekMBA, Nov 7 (from the pages posted on X) |
| Hinojosa | Nov 5: said Texas needs to stop what it is doing with data centers until residents have protections | American Bazaar, Nov 6 |
| Texas | Aug 3: Abbott ordered the PUC and ERCOT to audit data centers in ERCOT’s interconnection queue | Texas Tribune, Aug 3 |
| Texas | Sep 21: Abbott ordered TCEQ to halt data center permits until the audit is complete | Bracewell |
| Hinojosa | After the election: a moratorium would cover new permits, not projects already permitted (paraphrase of an interview) | Heatmap |
| CoreWeave | Q2 2026: active power “reach 1.5 GW” (infographic: 1.5GW+); contracted power about 3.7 GW; revenue $2575M (Q2 2025: $1212M); backlog about $104B, excluding more than $25B added in early Q3 | CoreWeave Q2 2026 release, Aug 11 |
| CoreWeave | Contracted power ~4.2GW as of Aug 11, 2026; 51 active data centers; backlog $104.2B | CoreWeave Q2 2026 infographic |
| CoreWeave | RPO $103.7B at June 30, 2026: 41% expected within 24 months, 39% in months 25–48, the rest in months 49–78 | CoreWeave 10-Q, Q2 2026 |
| CoreWeave | June 30, 2025: about 470 MW active; contracted power about 2.2 GW; backlog $30.1B | CoreWeave Q2 2025 release, Aug 12, 2025 |
| CoreWeave | 2026 capital spending guidance $35–39B, raised from $31–35B | Reuters, via The Star, Aug 12 |
| Helios | CoreWeave leases (Phases I–III): 526 MW critical IT, 800 MW gross; 15-year base term plus two 5-year options; $1.2B+ anticipated average annual revenue; Phase I 133 MW (200 MW gross), rent from Q2 2026; Phase II 260 MW, deliveries expected from Q2 2027 | Galaxy Q2 2026 results, Aug 5 |
| Helios | All 133 MW of Phase I delivered by end of Q2; Phase II fully financed and under construction; 830 MW approved at Helios II not yet leased; Q3 data center leasing revenue $79.1M | Galaxy Q3 2026 results, Oct 27 |
| Denton | Denton expansion adds about $1.2 billion of contracted revenue and brings the site’s critical IT load to approximately 260 MW; about 590 MW committed to CoreWeave across six sites | Core Scientific, Feb 26, 2025 |
| Plano | $1.6 billion, 450,000 sq ft data center, CoreWeave’s first in Texas | CoreWeave, July 25, 2023 |
| Market | Shares fell 9.83% to $43.66 on Nov 5, down 47.54% in a month; 2032 notes (9.625% coupon) yielded above 16% on Nov 6; five-year default swaps above 1,289 bp on Nov 5 and about 1,155 bp on Nov 6; Q3 results Nov 10 | 24/7 Wall St., Nov 7 |
The letter itself was read through Bloomberg’s, Investing.com’s and FourWeekMBA’s accounts; we could not open the pages posted on X. Not yet active: 4.2 − 1.5 = 2.7 GW; 2.7 ÷ 4.2 = 64%. The contracted figure is dated August 11 and the active figure June 30, and CoreWeave does not say whether its power figures are critical IT or gross. Growth: 1.5 ÷ 0.47 = 3.19; 4.2 ÷ 2.2 = 1.91; backlog 104.2 ÷ 30.1 = 3.46; revenue 2575 ÷ 1212 − 1 = 112.5%; 2575 × 4 = 10,300 ($M, a simple annualization). Helios: Phase III 526 − 133 − 260 = 133 MW; delivered 133 ÷ 526 = 25.3%; still to come 526 − 133 = 393 MW. Helios is 12.5% of 4.2 GW if both are on the same basis, which CoreWeave does not confirm; we do not use that figure in the text. RPO: 103.7 × 0.41 = 42.52; 103.7 × 0.39 = 40.44; remainder 20.74 ($B). The month ranges under the RPO chart count from June 30, 2026.
Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.